Interconnection queue in New Jersey (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown151,118 MW
Active in queue1,118 MW15 requests
Agreement signed0.0 MW0 requests
Withdrawn9625 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-260, Camden County
Battery storage Β· Haddy Energy Storage LLC
300 MWIn study Camden, NJPJM Jan 2025target 2025
Nuclear project AH1-710, Salem County
Nuclear Β· PSEG Nuclear LLC
257 MWIn study Salem, NJPJM Apr 2025
Gas project AH1-722, Union County
Gas Β· Parkway Generation Operating LLC
158 MWIn study Union, NJPJM Apr 2025
Gas project AH1-715, Union County
Gas Β· Parkway Generation Operating LLC
149 MWIn study Union, NJPJM Apr 2025
Gas project AH1-703, Bergen County
Gas Β· Parkway Generation Operating LLC
51.3 MWIn study Bergen, NJPJM Apr 2025
Solar project AG2-616, Salem County
Solar Β· Goldenrod Energy Center, LLC
50.0 MWIn study Salem, NJPJM Mar 2025target 2023
Solar project AG2-016, Ocean County
Solar Β· Lacey Holding / Ocean View Acres
19.8 MWIn study Ocean, NJPJM Mar 2025target 2021
Solar project AG2-625, Warren County
Solar Β· Chamberlain West Solar Farm LLC
19.6 MWIn study Warren, NJPJM Feb 2025target 2021
Heritage Solar Farm
Solar Β· Heritage Solar Farm, LLC
19.3 MWIn study Ocean, NJPJM Mar 2025target 2022
Port Belford Solar Farm
Solar Β· Port Belford Solar Farm, LLC
19.3 MWIn study Monmouth, NJPJM Jan 2025target 2022
Kober Solar Farm
Solar Β· CEP NJ KOBER LAND LLC
19.3 MWIn study Warren, NJPJM Feb 2025target 2022
Solar project AG2-297, Cumberland County
Solar Β· Calpine Mid-Atlantic Development, LLC
19.0 MWIn study Cumberland, NJPJM Feb 2025target 2023
Solar project AH1-641, Salem County
Solar Β· Goldenrod Energy Center, LLC
15.0 MWIn study Salem, NJPJM Mar 2025target 2023
Solar project AG2-626, Warren County
Solar Β· Chamberlain East Solar Farm LLC
12.5 MWIn study Warren, NJPJM Feb 2025target 2021
Solar project AH1-054, Ocean County
Solar Β· Pasadena Pemberton Solar Farm, LLC
8.3 MWIn study Ocean, NJPJM Feb 2025target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)