United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Jersey (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown197,831 MW
Active in queue7,831 MW19 requests
Agreement signed0.0 MW0 requests
Withdrawn106,761 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AI1-001, Monmouth County
Offshore wind
2,100 MWIn study Monmouth, NJPJM Apr 2022target 2029
Offshore wind project AI1-109, Middlesex County
Offshore wind
1,310 MWIn study Middlesex, NJPJM Sep 2022target 2029
Offshore wind project AI1-111, Middlesex County
Offshore wind
1,310 MWIn study Middlesex, NJPJM Sep 2022target 2029
Offshore wind project AI1-110, Monmouth County
Offshore wind
1,310 MWIn study Monmouth, NJPJM Sep 2022target 2029
Battery storage project AH2-333, Salem County
Battery storage
415 MWIn study Salem, NJPJM Mar 2022target 2025
Battery storage project AH2-334, Camden County
Battery storage
300 MWIn study Camden, NJPJM Mar 2022target 2025
Battery storage project AI1-187, Hunterdon County
Battery storage
280 MWIn study Hunterdon, NJPJM Sep 2022target 2027
Battery storage project AH2-378A, Gloucester County
Battery storage
200 MWIn study Gloucester, NJPJM Mar 2022target 2025
Solar project AI1-137, Warren County
Solar
155 MWIn study Warren, NJPJM Sep 2022target 2025
Battery storage project AH2-132, Salem County
Battery storage
117 MWIn study Salem, NJPJM Mar 2022target 2024
Battery storage project AH2-131, Gloucester County
Battery storage
104 MWIn study Gloucester, NJPJM Feb 2022target 2025
Battery storage project AH2-269, Ocean County
Battery storage
100 MWIn study Ocean, NJPJM Mar 2022target 2026
Solar project AI1-120, Warren County
Solar
51.6 MWIn study Warren, NJPJM Sep 2022target 2025
Solar project AI1-118, Warren County
Solar
37.6 MWIn study Warren, NJPJM Sep 2022target 2025
Battery storage project AH2-127, Burlington County
Battery storage
18.0 MWIn study Burlington, NJPJM Feb 2022target 2023
Solar project AI1-033, Somerset County
Solar
8.0 MWIn study Somerset, NJPJM Apr 2022target 2026
Solar project AH2-412, Cumberland County
Solar
7.4 MWIn study Cumberland, NJPJM Mar 2022target 2022
Solar project AI1-122, Sussex County
Solar
5.9 MWIn study Sussex, NJPJM Sep 2022target 2025
Solar project AH2-109
Solar
1.5 MWIn study NJPJM Feb 2022target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)