United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown427,050 MW
Active in queue1,419 MW5 requests
Agreement signed21.6 MW2 requests
Withdrawn427,050 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

42 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project AE1-034, Atlantic County
Onshore wind
1,104 MWWithdrawn / abandoned Atlantic, NJPJM Jun 2018target 2024
Offshore wind project AE2-024, Ocean County
Offshore wind
882 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2025
Offshore wind project AE1-238, Monmouth County
Offshore wind
816 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2018target 2024
Gas project AD2-171, Hunterdon County
Gas
700 MWWithdrawn / abandoned Hunterdon, NJPJM Mar 2018target 2023
Atlantic Shores Offshore Wind Project 1
Offshore wind
605 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Atlantic Shores Offshore Wind Project 1
Offshore wind
605 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Gas project AE2-012, Middlesex County
Gas
570 MWWithdrawn / abandoned Middlesex, NJPJM Nov 2018target 2023
Offshore wind project AE2-023, Atlantic County
Offshore wind
445 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2024
Offshore wind project AE2-025, Ocean County
Offshore wind
445 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2026
Atlantic Shores Offshore Wind Project 1
Offshore wind
300 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Solar + storage project AE1-055, Hudson County
Solar + storage
134 MWWithdrawn / abandoned Hudson, NJPJM Jul 2018target 2021
Gas project AD2-165, Middlesex County
Gas
105 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2018target 2021
Buckshutem Solar I
Solar
59.7 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2018target 2027
Battery storage project AE1-161, Cumberland County
Battery storage
50.0 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2018target 2021
Nabb Solar Project
Solar
49.7 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2018target 2024
Battery storage project AD2-211, Monmouth County
Battery storage
20.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2018target 2018
Battery storage project AE1-115, Salem County
Battery storage
20.0 MWWithdrawn / abandoned Salem, NJPJM Sep 2018target 2021
Battery storage project AE1-062, Camden County
Battery storage
20.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2018target 2020
Battery storage project AE1-244, Atlantic County
Battery storage
19.8 MWWithdrawn / abandoned Atlantic, NJPJM Sep 2018target 2020
Solar project AE1-126, Bergen County
Solar
19.8 MWWithdrawn / abandoned Bergen, NJPJM Sep 2018target 2019
Solar project AD2-052, Salem County
Solar
10.0 MWWithdrawn / abandoned Salem, NJPJM Jan 2018target 2019
Solar project AD2-037, Hunterdon County
Solar
7.5 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2018target 2019
Panther Branch Storage
Battery storage
5.5 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2018target 2025
Solar project AD2-204, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Mar 2018target 2019
Solar project AE1-083, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Aug 2018target 2019
Solar project AE2-015, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Nov 2018target 2020
Glassboro RE Solar
Solar
4.4 MWWithdrawn / abandoned Gloucester, NJPJM Sep 2018target 2022
Battery storage project AE1-203, Sussex County
Battery storage
4.0 MWWithdrawn / abandoned Sussex, NJPJM Sep 2018target 2019
Solar project AE2-016, Burlington County
Solar
3.5 MWWithdrawn / abandoned Burlington, NJPJM Nov 2018target 2020
Solar project AE2-018, Mercer County
Solar
3.5 MWWithdrawn / abandoned Mercer, NJPJM Dec 2018target 2020
Solar project AE2-011, Camden County
Solar
3.1 MWWithdrawn / abandoned Camden, NJPJM Nov 2018target 2020
Solar project AE1-046, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2018target 2019
Solar project AD2-069, Burlington County
Solar
3.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2018target 2019
Solar project AE1-045, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2018target 2019
Solar project AE1-063, Hunterdon County
Solar
3.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jul 2018target 2019
Glassboro LF Solar
Solar
2.0 MWWithdrawn / abandoned Gloucester, NJPJM Sep 2018target 2024
Battery storage project AD2-209, Hunterdon County
Battery storage
2.0 MWWithdrawn / abandoned Hunterdon, NJPJM Mar 2018target 2018
South Jefferson Road Storage
Battery storage
2.0 MWWithdrawn / abandoned Morris, NJPJM Mar 2018target 2020
Solar project AE1-223, Burlington County
Solar
1.9 MWWithdrawn / abandoned Burlington, NJPJM Sep 2018target 2018
Solar project AD2-064, Camden County
Solar
1.3 MWWithdrawn / abandoned Camden, NJPJM Feb 2018target 2019
Solar project AE1-043, Gloucester County
Solar
1.0 MWWithdrawn / abandoned Gloucester, NJPJM Jul 2018target 2018
State Route 57 Solar
Solar
0.8 MWWithdrawn / abandoned Warren, NJPJM Dec 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)