United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nevada (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown183,053 MW
Active in queue755 MW4 requests
Agreement signed755 MW4 requests
Withdrawn183,053 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Copper Rays
Solar
722 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Solar project Company 148, Clark County
Solar
440 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2018
Southland
Solar
380 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
Copper MTN Solar 5
Solar + storage
277 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
Re Prism
Solar
209 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2019
South Ridge
Solar
205 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Yellow Pine 1
Solar
153 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2019
Solar project Company 149, Clark County
Solar
126 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2019
Solar project Company HI, Nye County
Solar
100 MWWithdrawn / abandoned Nye, NVWest Sep 2016target 2018
Pahrump Solar
Solar
87.5 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2020
Solar project Company HB, Pershing County
Solar
70.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2016target 2024
Desert Obsidian
Solar
67.2 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2020
Solar project Company HH, Pershing County
Solar
50.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2016target 2020
Other project Company 150, Clark County
Other
43.5 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2021
Geothermal project Company HF, Lander County
Geothermal
38.5 MWWithdrawn / abandoned Lander, NVWest May 2016target 2019
Geothermal project Company HG, Pershing County
Geothermal
38.5 MWWithdrawn / abandoned Pershing, NVWest May 2016target 2024
Geothermal project Company HC, Mineral County
Geothermal
25.0 MWWithdrawn / abandoned Mineral, NVWest Mar 2016target 2018
Geothermal project Company HJ, Churchill County
Geothermal
20.0 MWWithdrawn / abandoned Churchill, NVWest Sep 2016target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)