United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Nevada (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown269,088 MW
Active in queue17.6 GW51 requests
Agreement signed8,552 MW25 requests
Withdrawn183,850 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

26 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Water Rock Solar 2
Solar + storage
1,034 MWIn study Nye, NVCAISO Apr 2021target 2028
Larrea Solar
Solar + storage
614 MWIn study Clark, NVCAISO Apr 2021target 2028
Solar + storage project Company 201, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar + storage project Company 200, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Wind + storage project Company LV, White Pine County
Wind + storage
600 MWPaused / redesign White Pine, NVWest Sep 2021target 2025
Solar + storage project Company LW, Mineral County
Solar + storage
550 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Sterling
Solar + storage
500 MWIn study Clark, NVCAISO Apr 2021target 2031
Solar + storage project Company ME, Lyon County
Solar + storage
500 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Battery storage project Company 206, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar + storage project Company LX, Mineral County
Solar + storage
400 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Dandelion Hybrid Solar
Solar + storage
334 MWIn study Nye, NVCAISO Apr 2021target 2027
Solar + storage project Company LL, Pershing County
Solar + storage
300 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Solar + storage project Company MJ, Lyon County
Solar + storage
300 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Delamar Energy Storage 2
Battery storage
256 MWIn study Clark, NVCAISO Apr 2021target 2027
Solar + storage project Company 208, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar + storage project Company LD, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Battery storage project Company 202, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project Company LZ, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Solar + storage project Company MK, Lyon County
Solar + storage
200 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Solar + storage project Company LC, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Solar + storage project Company LY, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Solar + storage project Company 207, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar + storage project Company LE, Pershing County
Solar + storage
200 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Battery storage project Company 204, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Battery storage project Company 210, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Solar + storage project Company 209, Clark County
Solar + storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)