United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nebraska (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown299,654 MW
Active in queue1,704 MW8 requests
Agreement signed1,204 MW5 requests
Withdrawn299,654 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

29 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2018-18, Banner County
Onshore wind
1,000 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Solar project GEN-2018-045, Banner County
Solar
550 MWWithdrawn / abandoned Banner, NESPP May 20182021
Onshore wind project GI-2018-17, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-16, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Solar project GEN-2018-044, Antelope County
Solar
500 MWWithdrawn / abandoned Antelope, NESPP May 20182025
Onshore wind project GEN-2018-110, Nemaha County
Onshore wind
500 MWWithdrawn / abandoned Nemaha, NESPP Nov 2018target 2023
Onshore wind project GI-2018-10, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-7, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-12, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-8, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Solar project GEN-2018-066, Lancaster County
Solar
400 MWWithdrawn / abandoned Lancaster, NESPP Oct 2018target 2022
Onshore wind project GEN-2018-119, Johnson County
Onshore wind
400 MWWithdrawn / abandoned Johnson, NESPP Nov 2018target 2023
Onshore wind project GEN-2018-046, Banner County
Onshore wind
400 MWWithdrawn / abandoned Banner, NESPP May 20182025
Onshore wind project GI-2018-14, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-13, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GEN-2018-068, Madison County
Onshore wind
302 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Onshore wind project GEN-2018-017, Keith County
Onshore wind
302 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Onshore wind project GEN-2018-042, Johnson County
Onshore wind
300 MWWithdrawn / abandoned Johnson, NESPP May 20182025
Onshore wind project GI-2018-15, Banner County
Onshore wind
300 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GEN-2018-083, Madison County
Onshore wind
250 MWWithdrawn / abandoned Madison, NESPP Nov 2018target 2027
Battery storage project GEN-2018-036, Scotts Bluff County
Battery storage
200 MWWithdrawn / abandoned Scotts Bluff, NESPP May 20182023
Onshore wind project GI-2018-11, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-9, Banner County
Onshore wind
199 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Battery storage project GEN-2018-090, Washington County
Battery storage
125 MWWithdrawn / abandoned Washington, NESPP Nov 2018target 2027
Onshore wind project GEN-2018-130, Knox County
Onshore wind
122 MWWithdrawn / abandoned Knox, NESPP Nov 2018target 2020
Solar project GEN-2018-056, Knox County
Solar
103 MWWithdrawn / abandoned Knox, NESPP May 2018target 2028
Onshore wind project GEN-2018-016, Keith County
Onshore wind
101 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Onshore wind project GEN-2018-012, Wayne County
Onshore wind
74.1 MWWithdrawn / abandoned Wayne, NESPP Apr 20182025
Onshore wind project GEN-2018-065, Madison County
Onshore wind
19.8 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)