Withdrawn queue requests in Nebraska (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown152,772 MW
Active in queue290 MW3 requests
Agreement signed290 MW3 requests
Withdrawn152,772 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-159, Stanton County
Onshore wind
428 MWWithdrawn / abandoned Stanton, NESPP Nov 2016target 2020
Onshore wind project GEN-2016-106, Keith County
Onshore wind
400 MWWithdrawn / abandoned Keith, NESPP Nov 20162020
Onshore wind project GEN-2016-116, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Nov 2016target 2019
Onshore wind project GEN-2017-001, Custer County
Onshore wind
250 MWWithdrawn / abandoned Custer, NESPP Dec 2016target 2023
Onshore wind project GEN-2016-096, Fillmore County
Onshore wind
228 MWWithdrawn / abandoned Fillmore, NESPP Nov 20162020
Onshore wind project GEN-2016-165, Knox County
Onshore wind
202 MWWithdrawn / abandoned Knox, NESPP Nov 2016target 2019
Solar project GEN-2016-079, Cheyenne County
Solar
160 MWWithdrawn / abandoned Cheyenne, NESPP Jun 2016target 2019
Onshore wind project GEN-2016-055, Webster County
Onshore wind
127 MWWithdrawn / abandoned Webster, NESPP Mar 2016target 2018
Onshore wind project GEN-2016-026, Custer County
Onshore wind
120 MWWithdrawn / abandoned Custer, NESPP Mar 2016target 2018
Onshore wind project GEN-2016-064, Webster County
Onshore wind
116 MWWithdrawn / abandoned Webster, NESPP Mar 2016target 2017
Onshore wind project GEN-2016-109, Jefferson County
Onshore wind
102 MWWithdrawn / abandoned Jefferson, NESPP Nov 2016target 2019
Onshore wind project GEN-2016-025, Custer County
Onshore wind
100 MWWithdrawn / abandoned Custer, NESPP Mar 2016target 2018
Onshore wind project GEN-2016-034, Banner County
Onshore wind
90.0 MWWithdrawn / abandoned Banner, NESPP Mar 2016target 2018
Solar project GEN-2016-093, Scotts Bluff County
Solar
70.0 MWWithdrawn / abandoned Scotts Bluff, NESPP Oct 2016target 2018
Onshore wind project GEN-2016-027, Cherry County
Onshore wind
60.0 MWWithdrawn / abandoned Cherry, NESPP Mar 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)