Interconnection queue in Missouri (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,436 MW
Active in queue1,436 MW10 requests
Agreement signed936 MW8 requests
Withdrawn81,284 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1836, Callaway County
Solar
300 MWIn study Callaway, MOMISO Jun 2020target 2025
Onshore wind project GI-95, Dade County
Onshore wind
247 MWAgreement signed Dade, MOSoutheast Dec 2020target 2026
Solar project J1519, Bollinger County
Solar
200 MWIn study Bollinger, MOMISO Jun 2020target 2025
Solar project GEN-2020-088, Jasper County
Solar
150 MWAgreement signed Jasper, MOSPP Apr 2020target 2028
Solar + storage project GEN-2020-072, Henry County
Solar + storage
150 MWAgreement signed Henry, MOSPP Apr 2020target 2029
Solar project GI-93, Macon County
Solar
100 MWAgreement signed Macon, MOSoutheast Nov 2020target 2026
Solar project GI-90, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Jul 2020target 2027
Solar project GI-91, Carroll County
Solar
96.0 MWAgreement signed Carroll, MOSoutheast Jul 2020target 2027
Gas project GEN-2020-064, Jasper County
Gas
64.0 MWAgreement signed Jasper, MOSPP Apr 20202025
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)