United States βΊ Grid βΊ Interconnection queues βΊ Missouri
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Missouri (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J1836, Callaway County Solar |
300 MW | In study |
| Onshore wind project GI-95, Dade County Onshore wind |
247 MW | Agreement signed |
| Solar project J1519, Bollinger County Solar |
200 MW | In study |
| Solar project GEN-2020-088, Jasper County Solar |
150 MW | Agreement signed |
| Solar + storage project GEN-2020-072, Henry County Solar + storage |
150 MW | Agreement signed |
| Solar project GI-93, Macon County Solar |
100 MW | Agreement signed |
| Solar project GI-90, Randolph County Solar |
100 MW | Agreement signed |
| Solar project GI-91, Carroll County Solar |
96.0 MW | Agreement signed |
| Gas project GEN-2020-064, Jasper County Gas |
64.0 MW | Agreement signed |
| Gas project GEN-2020-061, Cass County Gas |
29.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)4 Β· 543 MW
- MISO (Midcontinent)2 Β· 500 MW
- SPP (Southwest Power Pool)4 Β· 393 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)