United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Missouri (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown92,125 MW
Active in queue2,125 MW9 requests
Agreement signed1,200 MW5 requests
Withdrawn479,349 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1026, Audrain County
Onshore wind
400 MWAgreement signed Audrain, MOMISO Mar 2018target 2023
Solar project J976, Warren County
Solar
300 MWUnder construction Warren, MOMISO Mar 2018target 2024
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Solar project J1145, Callaway County
Solar
250 MWAgreement signed Callaway, MOMISO Mar 2018target 2024
Solar project J1034, Stoddard County
Solar
225 MWUnder construction Stoddard, MOMISO Mar 2018target 2024
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Solar project J1107, Cape Girardeau County
Solar
200 MWUnder construction Cape Girardeau, MOMISO Mar 2018target 2023
Solar project J1087, Scott County
Solar
200 MWUnder construction Scott, MOMISO Mar 2018target 2023
Battery storage project GEN-2018-031, Jackson County
Battery storage
50.0 MWAgreement signed Jackson, MOSPP May 2018target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)