United States βΊ Grid βΊ Interconnection queues βΊ Missouri
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Missouri (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2020-053, Newton County Onshore wind |
240 MW | Withdrawn / abandoned |
| Solar project GI-94, Jasper County Solar |
225 MW | Withdrawn / abandoned |
| Solar project J1681, Maries County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1585, Moniteau County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-92, Howard County Onshore wind |
170 MW | Withdrawn / abandoned |
| Solar project J1764, Perry County Solar |
125 MW | Withdrawn / abandoned |
| Solar project GI-89, Scott County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project J1636, Pike County Solar |
44.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)4 Β· 569 MW
- Southeast (non-ISO utilities)3 Β· 475 MW
- SPP (Southwest Power Pool)1 Β· 240 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)