United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown152,575 MW
Active in queue550 MW4 requests
Agreement signed0.0 MW0 requests
Withdrawn152,575 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1315, Cottonwood County
Onshore wind
600 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2019target 2022
Other project J1349, Cottonwood County
Other
335 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2019target 2023
Solar project J1337, Sherburne County
Solar
300 MWWithdrawn / abandoned Sherburne, MNMISO Apr 2019target 2022
Solar project J1395, Lyon County
Solar
200 MWWithdrawn / abandoned Lyon, MNMISO Apr 2019target 2023
Solar project J1298, Freeborn County
Solar
150 MWWithdrawn / abandoned Freeborn, MNMISO Apr 2019target 2021
Battery storage project J1446, Wright County
Battery storage
150 MWWithdrawn / abandoned Wright, MNMISO Apr 2019target 2022
Onshore wind project J1371, Yellow Medicine County
Onshore wind
150 MWWithdrawn / abandoned Yellow Medicine, MNMISO Apr 2019target 2023
Onshore wind project J1487, Freeborn County
Onshore wind
120 MWWithdrawn / abandoned Freeborn, MNMISO Apr 2019target 2021
Solar project J1300, Nobles County
Solar
120 MWWithdrawn / abandoned Nobles, MNMISO Apr 2019target 2021
Battery storage project J1468, Dakota County
Battery storage
100 MWWithdrawn / abandoned Dakota, MNMISO Apr 2019target 2022
Solar project J1228, Faribault County
Solar
100 MWWithdrawn / abandoned Faribault, MNMISO Apr 2019target 2023
Solar project J1473, Chisago County
Solar
100 MWWithdrawn / abandoned Chisago, MNMISO Apr 2019target 2022
Solar project J1212, Murray County
Solar
60.0 MWWithdrawn / abandoned Murray, MNMISO Apr 2019target 2023
Solar project J1461, Carver County
Solar
50.0 MWWithdrawn / abandoned Carver, MNMISO Apr 2019target 2022
Battery storage project J1230, Wadena County
Battery storage
40.0 MWWithdrawn / abandoned Wadena, MNMISO Apr 2019target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)