United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Michigan (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown112,701 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn112,701 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J268, Genesee County
Gas
801 MWWithdrawn / abandoned Genesee, MIMISO Jan 2013
Gas project J275, Midland County
Gas
700 MWWithdrawn / abandoned Midland, MIMISO Mar 2013target 2015
Onshore wind project J308, Sanilac County
Onshore wind
301 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2013target 2016
Gas project J271, Montcalm County
Gas
232 MWWithdrawn / abandoned Montcalm, MIMISO Mar 2013
Onshore wind project J307, Osceola County
Onshore wind
201 MWWithdrawn / abandoned Osceola, MIMISO Nov 2013
Onshore wind project J267, Tuscola County
Onshore wind
125 MWWithdrawn / abandoned Tuscola, MIMISO Jan 2013target 2015
Gas project J317, Marquette County
Gas
112 MWWithdrawn / abandoned Marquette, MIMISO Nov 2013
Onshore wind project J296, Presque Isle County
Onshore wind
69.3 MWWithdrawn / abandoned Presque Isle, MIMISO Sep 2013
Onshore wind project J300, Mackinac County
Onshore wind
60.0 MWWithdrawn / abandoned Mackinac, MIMISO Nov 2013
Onshore wind project J281, Huron County
Onshore wind
50.0 MWWithdrawn / abandoned Huron, MIMISO May 2013target 2013
Onshore wind project J282, Huron County
Onshore wind
50.0 MWWithdrawn / abandoned Huron, MIMISO May 2013target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)