United States β€Ί Grid β€Ί Interconnection queues β€Ί Massachusetts

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Massachusetts (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16261 MW
Active in queue834 MW2 requests
Agreement signed6.8 MW1 requests
Withdrawn191,792 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Cranberry Point Energy Storage
Battery storage
150 MWOperating Plymouth, MAISO-NE Mar 2018target 2025
Crystal Lake Substation - NG Western MA Area Cluster Study
Solar
24.7 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Wendell Depot Substation - NG Western MA Area Cluster Study
Solar
15.0 MWOperating Franklin, MAISO-NE Dec 2018target 2021
Solar with Battery
Solar + storage
10.0 MWOperating Worcester, MAISO-NE Sep 2018target 2021
Solar
Solar
9.5 MWOperating Plymouth, MAISO-NE Jan 2018target 2019
N. Oxford Substation - NG Western MA Area Cluster Study
Solar
8.7 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Belchertown Substation - NG Western MA Area Cluster Study
Solar
8.0 MWOperating Hampden, MAISO-NE Dec 2018target 2021
Combined Reciprocating, Solar and Battery
Solar + storage
7.8 MWOperating Middlesex, MAISO-NE Aug 2018target 2019
Kearsarge Solar with battery
Solar + storage
5.4 MWOperating Norfolk, MAISO-NE Aug 2018target 2021
Solar
Solar
4.9 MWOperating Plymouth, MAISO-NE Aug 2018target 2019
Westminster - NG Western MA Area Cluster Study
Solar
4.9 MWOperating Worcester, MAISO-NE Dec 2018target 2021
Chestnut Hill 702 Substation - NG Western MA Area Cluster Study
Solar
3.3 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Five Corners Substation - NG Western MA Area Cluster Study
Solar
3.0 MWOperating Hampshire, MAISO-NE Dec 2018target 2021
Leicester - NG Western MA Area Cluster Study
Solar
2.6 MWOperating Worcester, MAISO-NE Dec 2018target 2021
Solar
Solar
1.9 MWOperating Bristol, MAISO-NE Jan 2018target 2020
Solar with battery addition
Solar + storage
1.3 MWOperating Hampshire, MAISO-NE Jun 2018target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)