πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maine (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,338 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn91,338 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wind
Onshore wind
376 MWWithdrawn / abandoned Aroostook, MEISO-NE Dec 2016target 2019
Wind
Onshore wind
246 MWWithdrawn / abandoned Franklin, MEISO-NE Jan 2016target 2019
Wind
Onshore wind
216 MWWithdrawn / abandoned Franklin, MEISO-NE Jan 2016target 2019
Solar
Solar
150 MWWithdrawn / abandoned York, MEISO-NE Oct 2016target 2022
Wind
Onshore wind
93.6 MWWithdrawn / abandoned Somerset, MEISO-NE Oct 2016target 2020
Solar
Solar
78.4 MWWithdrawn / abandoned Franklin, MEISO-NE Jun 2016target 2018
Solar
Solar
75.0 MWWithdrawn / abandoned Washington, MEISO-NE Oct 2016target 2022
Steam Turbines
Other
75.0 MWWithdrawn / abandoned Franklin, MEISO-NE Apr 2016target 2018
Hydro
Hydro
28.3 MWWithdrawn / abandoned Oxford, MEISO-NE Feb 2016target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)