OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Kentucky (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project LGE-GIS-2021-009, Hardin County Solar + storage |
200 MW | Paused / redesign |
| Solar + storage project AH2-021, Barren County Solar + storage |
150 MW | In study |
| Solar project LGE-GIS-2021-010, Marion County Solar |
120 MW | Agreement signed |
| Solar + storage project LGE-GIS-2021-020, Mccracken County Solar + storage |
120 MW | Agreement signed |
| Solar project LGE-GIS-2021-007, Mccracken County Solar |
120 MW | Paused / redesign |
| Battery storage project LGE-GIS-2021-013, Hardin County Battery storage |
120 MW | Agreement signed |
| Solar + storage project LGE-GIS-2021-018, Bath County Solar + storage |
110 MW | Paused / redesign |
| Solar + storage project LGE-GIS-2021-017, Mason County Solar + storage |
100 MW | Paused / redesign |
| Solar project LGE-GIS-2021-019, Boyle County Solar |
100 MW | Paused / redesign |
| Solar project AH2-002, Barren County Solar |
80.0 MW | In study |
| Solar project J1649, Mccracken County Solar |
60.0 MW | In study |
| Hydro project 476, Lyon County Hydro |
18.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)9 Β· 1,008 MW
- PJM (Mid-Atlantic, Midwest)2 Β· 230 MW
- MISO (Midcontinent)1 Β· 60.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)