United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Kentucky (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8388 MW
Active in queue86.0 MW1 requests
Agreement signed86.0 MW1 requests
Withdrawn8388 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project LGE-GIS-2017-006, Muhlenberg County
Solar
100 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Aug 2017target 2019
Gas project AD1-134
Gas
73.0 MWWithdrawn / abandoned KYPJM Sep 2017target 2020
Solar project AC2-069, Harrison County
Solar
60.0 MWWithdrawn / abandoned Harrison, KYPJM Feb 2017target 2019
Solar project AC2-114, Campbell County
Solar
49.9 MWWithdrawn / abandoned Campbell, KYPJM Mar 2017target 2019
Solar project LGE-GIS-2017-001, Hickman County
Solar
35.0 MWWithdrawn / abandoned Hickman, KYSoutheast Feb 2017target 2019
Solar project LGE-GIS-2017-003, Harrison County
Solar
35.0 MWWithdrawn / abandoned Harrison, KYSoutheast Apr 2017target 2021
Solar project LGE-GIS-2017-004, Harrison County
Solar
25.0 MWWithdrawn / abandoned Harrison, KYSoutheast Jun 2017target 2019
Solar project LGE-GIS-2017-005, Harrison County
Solar
10.0 MWWithdrawn / abandoned Harrison, KYSoutheast Aug 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)