United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
GAS Β· PJMGas project AD1-134
Gas project AD1-134 is a 73.0 MW gas request withdrawn in the PJM interconnection queue, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedApr 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD1-134
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- JK Smith 138 kV
- Location
- Kentucky
- Technology
- Gas: 73.0 MW
- Total requested
- 73.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 29 September 2017
- Proposed online date
- July 2020
- Withdrawn
- April 2019
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem