United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· SOUTHEAST

Solar project LGE-GIS-2017-006, Muhlenberg County

Solar project LGE-GIS-2017-006, Muhlenberg County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Muhlenberg County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LGE-GIS-2017-006
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
138 kV Green River substation (Alternate POI: Green River - Green River Tap 138 kV)
Location
Muhlenberg County, Kentucky
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
LGIA terminated
Queue status
Withdrawn
Entered queue
18 August 2017
Proposed online date
August 2019

Location

Marker shows the centre of Muhlenberg County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Muhlenberg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem