United States βΊ Grid βΊ Interconnection queues βΊ Illinois
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Illinois (2014 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Nuclear project J371, Ogle County Nuclear |
2,325 MW | Withdrawn / abandoned |
| Nuclear project J372, Rock Island County Nuclear |
1,373 MW | Withdrawn / abandoned |
| Gas project AA2-035, Grundy County Gas |
1,019 MW | Withdrawn / abandoned |
| Gas project J388, Vermilion County Gas |
800 MW | Withdrawn / abandoned |
| Gas project AA1-048, Grundy County Gas |
800 MW | Withdrawn / abandoned |
| Gas project Z2-041, Mchenry County Gas |
455 MW | Withdrawn / abandoned |
| Onshore wind project AA1-086, Macon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project Z2-086, Adams County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J375, Ford County Onshore wind |
124 MW | Withdrawn / abandoned |
| Gas project AA1-129, Cook County Gas |
27.0 MW | Withdrawn / abandoned |
| Battery storage project AA1-117, Kankakee County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AA1-116, Kankakee County Battery storage |
18.4 MW | Withdrawn / abandoned |
| Battery storage project Z2-090, Winnebago County Battery storage |
4.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)