United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown137,366 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn137,366 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project J371, Ogle County
Nuclear
2,325 MWWithdrawn / abandoned Ogle, ILMISO Jun 2014target 2016
Nuclear project J372, Rock Island County
Nuclear
1,373 MWWithdrawn / abandoned Rock Island, ILMISO Jun 2014target 2019
Gas project AA2-035, Grundy County
Gas
1,019 MWWithdrawn / abandoned Grundy, ILPJM Dec 2014target 2019
Gas project J388, Vermilion County
Gas
800 MWWithdrawn / abandoned Vermilion, ILMISO Sep 2014target 2018
Gas project AA1-048, Grundy County
Gas
800 MWWithdrawn / abandoned Grundy, ILPJM Aug 2014target 2018
Gas project Z2-041, Mchenry County
Gas
455 MWWithdrawn / abandoned Mchenry, ILPJM Feb 2014target 2018
Onshore wind project AA1-086, Macon County
Onshore wind
200 MWWithdrawn / abandoned Macon, ILPJM Oct 2014target 2017
Onshore wind project Z2-086, Adams County
Onshore wind
200 MWWithdrawn / abandoned Adams, ILPJM Apr 2014
Onshore wind project J375, Ford County
Onshore wind
124 MWWithdrawn / abandoned Ford, ILMISO Jul 2014target 2015
Gas project AA1-129, Cook County
Gas
27.0 MWWithdrawn / abandoned Cook, ILPJM Oct 2014target 2018
Battery storage project AA1-117, Kankakee County
Battery storage
20.0 MWWithdrawn / abandoned Kankakee, ILPJM Oct 2014target 2016
Battery storage project AA1-116, Kankakee County
Battery storage
18.4 MWWithdrawn / abandoned Kankakee, ILPJM Oct 2014target 2016
Battery storage project Z2-090, Winnebago County
Battery storage
4.0 MWWithdrawn / abandoned Winnebago, ILPJM Apr 2014target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)