πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Georgia (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown143,192 MW
Active in queue7,061 MW35 requests
Agreement signed3,192 MW14 requests
Withdrawn305,643 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project IC-1166, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1168, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1167, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Battery storage project IC-1223, Hall County
Battery storage
250 MWAgreement signed Hall, GASoutheast Dec 2023target 2028
Battery storage project IC-1222, Bartow County
Battery storage
250 MWAgreement signed Bartow, GASoutheast Dec 2023target 2027
Solar project IC-1206, Laurens County
Solar
225 MWAgreement signed Laurens, GASoutheast Nov 2023target 2028
Battery storage project IC-1187, Wilkinson County
Battery storage
220 MWAgreement signed Wilkinson, GASoutheast Oct 2023target 2027
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Solar project IC-1152, Washington County
Solar
200 MWAgreement signed Washington, GASoutheast Jul 2023target 2027
Solar project IC-1142, Baldwin County
Solar
183 MWAgreement signed Baldwin, GASoutheast May 2023target 2028
Solar project IC-1172, Jefferson County
Solar
128 MWAgreement signed Jefferson, GASoutheast Sep 2023target 2028
Battery storage project IC-1116, Carroll County
Battery storage
100 MWAgreement signed Carroll, GASoutheast Jan 2023target 2027
Solar + storage project IC-1199, Lowndes County
Solar + storage
3.5 MWAgreement signed Lowndes, GASoutheast Nov 2023target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)