United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,448 MW
Active in queue10.6 GW44 requests
Agreement signed0.0 MW0 requests
Withdrawn91,448 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GI-RSC-2025-01, Moffat County
Gas
307 MWWithdrawn / abandoned Moffat, COWest Jul 2025target 2029
Solar + storage project GI-CS-2025-01, Pueblo County
Solar + storage
199 MWWithdrawn / abandoned Pueblo, COWest Sep 2025target 2031
Solar + storage project GI-CS-2025-15, El Paso County
Solar + storage
195 MWWithdrawn / abandoned El Paso, COWest Sep 2025target 2028
Battery storage project GI-CS-2025-06, Rio Blanco County
Battery storage
150 MWWithdrawn / abandoned Rio Blanco, COWest Sep 2025target 2029
Battery storage project GI-CS-2025-14, Pueblo County
Battery storage
150 MWWithdrawn / abandoned Pueblo, COWest Sep 2025target 2028
Battery storage project GI-SISS-2025-02, Logan County
Battery storage
150 MWWithdrawn / abandoned Logan, COWest Jun 2025
Battery storage project GI-SISS-2025-01, Kit Carson County
Battery storage
100 MWWithdrawn / abandoned Kit Carson, COWest Jun 2025target 2028
Battery storage project GI-2025-11, Mesa County
Battery storage
100 MWWithdrawn / abandoned Mesa, COWest Apr 2025target 2028
Solar + storage project GI-CS-2025-13, Weld County
Solar + storage
97.0 MWWithdrawn / abandoned Weld, COWest Sep 2025target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)