πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown284,892 MW
Active in queue1,600 MW4 requests
Agreement signed1,400 MW3 requests
Withdrawn284,892 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

28 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2016-27, Elbert County
Onshore wind
640 MWWithdrawn / abandoned Elbert, COWest Nov 2016target 2019
Onshore wind project GI-2016-6, Lincoln County
Onshore wind
600 MWWithdrawn / abandoned Lincoln, COWest Apr 2016target 2018
Onshore wind project GI-2016-25, Kit Carson County
Onshore wind
500 MWWithdrawn / abandoned Kit Carson, COWest Oct 2016target 2020
Solar project GI-2016-9, Alamosa County
Solar
480 MWWithdrawn / abandoned Alamosa, COWest Apr 2016target 2023
Onshore wind project GI-2016-20, Elbert County
Onshore wind
300 MWWithdrawn / abandoned Elbert, COWest Sep 2016target 2019
Solar project GI-2016-7, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Apr 2016target 2018
Solar project GI-2016-5, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Apr 2016target 2019
Solar project GI-2016-13, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Jun 2016target 2020
Solar project GI-2016-21, Lincoln County
Solar
200 MWWithdrawn / abandoned Lincoln, COWest Sep 2016target 2019
Onshore wind project GI-2016-19, Lincoln County
Onshore wind
150 MWWithdrawn / abandoned Lincoln, COWest Sep 2016target 2019
Solar project GI-2016-23, Adams County
Solar
150 MWWithdrawn / abandoned Adams, COWest Oct 2016target 2019
Solar project GI-2016-29, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Nov 2016target 2019
Solar project GI-2016-2, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Feb 2016target 2018
Solar project GI-2016-18, Pueblo County
Solar
120 MWWithdrawn / abandoned Pueblo, COWest Aug 2016target 2018
Solar project GI-2016-11, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Jun 2016target 2018
Solar project GI-2016-22, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Sep 2016target 2019
Solar project GI-2016-16, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Aug 2016target 2018
Solar project GI-2016-12, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Jun 2016target 2019
Solar project GI-2016-1, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2016target 2018
Solar project GI-2016-31, Morgan County
Solar
51.8 MWWithdrawn / abandoned Morgan, COWest Dec 2016target 2019
Solar project GI-2016-28, Mesa County
Solar
51.8 MWWithdrawn / abandoned Mesa, COWest Nov 2016target 2019
Solar project GI-2016-32, Arapahoe County
Solar
51.8 MWWithdrawn / abandoned Arapahoe, COWest Dec 2016target 2019
Solar project GI-2016-17, Pueblo County
Solar
50.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2016target 2018
Solar project GI-2016-26, Saguache County
Solar
50.0 MWWithdrawn / abandoned Saguache, COWest Oct 2016target 2018
Solar project GI-2016-24, Adams County
Solar
50.0 MWWithdrawn / abandoned Adams, COWest Oct 2016target 2019
Solar project GI-2016-8, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Apr 2016target 2018
Solar project GI-2016-30, Weld County
Solar
30.0 MWWithdrawn / abandoned Weld, COWest Nov 2016target 2019
Gas project GI-2016-10, Weld County
Gas
6.5 MWWithdrawn / abandoned Weld, COWest May 2016target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)