Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown102,551 MW
Active in queue2,551 MW10 requests
Agreement signed0.0 MW0 requests
Withdrawn111,312 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J2841, Independence County
Onshore wind
500 MWIn study Independence, ARMISO Sep 2022target 2025
Onshore wind project J3597, Lonoke County
Onshore wind
348 MWIn study Lonoke, ARMISO Apr 2024target 2028
Onshore wind project J3982, Lonoke County
Onshore wind
320 MWIn study Lonoke, ARMISO Dec 2024target 2030
Onshore wind project J2613, Jackson County
Onshore wind
300 MWIn study Jackson, ARMISO Sep 2022target 2025
Onshore wind project J2641, Jackson County
Onshore wind
200 MWIn study Jackson, ARMISO Sep 2022target 2025
Onshore wind project J2577, Cross County
Onshore wind
200 MWIn study Cross, ARMISO Sep 2022target 2025
Onshore wind project J3292, Phillips County
Onshore wind
193 MWIn study Phillips, ARMISO Apr 2024target 2028
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Onshore wind project J2437, Lee County
Onshore wind
175 MWIn study Lee, ARMISO Sep 2022target 2027
Onshore wind project J1842, Cross County
Onshore wind
135 MWIn study Cross, ARMISO Oct 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)