Withdrawn queue requests in Arkansas (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown174,765 MW
Active in queue850 MW6 requests
Agreement signed0.0 MW0 requests
Withdrawn174,765 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 597, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar + storage project 592, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar + storage project 594, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar + storage project 593, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar project 599, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project 598, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project GEN-2022-239, Hempstead County
Solar
350 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Battery storage project GEN-2023-235, Benton County
Battery storage
250 MWWithdrawn / abandoned Benton, ARSPP Oct 20232025
Battery storage project GEN-2022-241, Hempstead County
Battery storage
200 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Battery storage project GEN-2022-240, Hempstead County
Battery storage
200 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Solar project GEN-2023-180, Sebastian County
Solar
150 MWWithdrawn / abandoned Sebastian, ARSPP Oct 2023target 2028
Battery storage project GEN-2023-056, Van Buren County
Battery storage
150 MWWithdrawn / abandoned Van Buren, ARSPP Oct 2023target 2028
Battery storage project GEN-2023-213, Benton County
Battery storage
100 MWWithdrawn / abandoned Benton, ARSPP Oct 2023target 2028
Solar + storage project GEN-2023-151, Hempstead County
Solar + storage
100 MWWithdrawn / abandoned Hempstead, ARSPP Oct 2023target 2028
Solar project GEN-2022-218, Sharp County
Solar
95.0 MWWithdrawn / abandoned Sharp, ARSPP Mar 2023target 2028
Battery storage project GEN-2023-232, Benton County
Battery storage
90.0 MWWithdrawn / abandoned Benton, ARSPP Oct 20232025
Solar + storage project GEN-2022-099, Benton County
Solar + storage
80.0 MWWithdrawn / abandoned Benton, ARSPP Mar 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)