United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-056, Van Buren County
Battery storage project GEN-2023-056, Van Buren County is a 150 MW battery storage request withdrawn in the SPP interconnection queue, in Van Buren County, Arkansas, connecting to SWPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-056
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SWPA
- Connection point (POI)
- Van Buren 161 kV
- Location
- Van Buren County, Arkansas
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- May 2028
- Withdrawn
- August 2025
Location
Marker shows the centre of Van Buren County; the queue data does not give exact sites.