United States βΊ Grid βΊ Interconnection queues βΊ Arizona
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Arizona (2017 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project Q41, Pinal County Gas |
1,213 MW | Withdrawn / abandoned |
| Gas project Q260, Pinal County Gas |
900 MW | Withdrawn / abandoned |
| Gas project Q261, Maricopa County Gas |
900 MW | Withdrawn / abandoned |
| Harquahala Flats Solar + storage |
900 MW | Withdrawn / abandoned |
| Gas project Q39, Pinal County Gas |
864 MW | Withdrawn / abandoned |
| Gas project Q257, Pinal County Gas |
500 MW | Withdrawn / abandoned |
| Gas project Q251, Pinal County Gas |
495 MW | Withdrawn / abandoned |
| Harquahala Sun Solar + storage |
313 MW | Withdrawn / abandoned |
| Gas project Q40, Pinal County Gas |
220 MW | Withdrawn / abandoned |
| Gas project Q42, Pinal County Gas |
197 MW | Withdrawn / abandoned |
| Darlington Balley Solar Energy 1 Solar + storage |
185 MW | Withdrawn / abandoned |
| Sun Streams Solar 3 Solar |
155 MW | Withdrawn / abandoned |
| Solar + storage project Q253, Pinal County Solar + storage |
140 MW | Withdrawn / abandoned |
| Solar project 54, Pinal County Solar Β· SunPower |
105 MW | Withdrawn / abandoned |
| Solar project 55, Pima County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project 56, Apache County Onshore wind |
99.1 MW | Withdrawn / abandoned |
| Battery storage project Q258, Maricopa County Battery storage |
37.5 MW | Withdrawn / abandoned |
| Solar project Q217, Yuma County Solar |
35.0 MW | Withdrawn / abandoned |
| Battery storage project Q263, Pinal County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project Q262, Pinal County Solar |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)