Requests shown223,196 MW
Active in queue3,196 MW22 requests
Agreement signed536 MW2 requests
Withdrawn272,676 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IC-1059, Pike County
Solar + storage
420 MWPaused / redesign Pike, ALSoutheast Sep 2022target 2027
Battery storage project IC-1102, Montgomery County
Battery storage
400 MWPaused / redesign Montgomery, ALSoutheast Dec 2022target 2026
Solar project IC-1071, Perry County
Solar
336 MWAgreement signed Perry, ALSoutheast Sep 2022target 2027
Battery storage project IC-1091, Mobile County
Battery storage
300 MWPaused / redesign Mobile, ALSoutheast Nov 2022target 2027
Battery storage project 514, Dekalb County
Battery storage
200 MWAgreement signed Dekalb, ALSoutheast Aug 2022target 2028
Solar + storage project IC-1040, Hale County
Solar + storage
170 MWPaused / redesign Hale, ALSoutheast Jun 2022target 2027
Solar + storage project IC-1101, Perry County
Solar + storage
150 MWPaused / redesign Perry, ALSoutheast Dec 2022target 2027
Solar project IC-1043, Coosa County
Solar
100 MWPaused / redesign Coosa, ALSoutheast Jul 2022target 2030
Solar + storage project IC-1072, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Oct 2022target 2027
Solar + storage project IC-1054, Pike County
Solar + storage
80.0 MWPaused / redesign Pike, ALSoutheast Aug 2022target 2027
Solar project IC-1066, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Sep 2022target 2030
Solar project IC-1051, Escambia County
Solar
80.0 MWPaused / redesign Escambia, ALSoutheast Aug 2022target 2027
Solar project IC-1083, Marengo County
Solar
80.0 MWPaused / redesign Marengo, ALSoutheast Oct 2022target 2026
Solar project IC-1039, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast May 2022target 2026
Solar + storage project IC-1060, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar + storage project IC-1053, Hale County
Solar + storage
80.0 MWPaused / redesign Hale, ALSoutheast Aug 2022target 2027
Solar + storage project IC-1087, Russell County
Solar + storage
80.0 MWPaused / redesign Russell, ALSoutheast Nov 2022target 2026
Solar + storage project IC-1052, Lee County
Solar + storage
80.0 MWPaused / redesign Lee, ALSoutheast Aug 2022target 2026
Solar project IC-1036, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast May 2022target 2027
Solar + storage project IC-1061, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar project IC-1075, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast Oct 2022target 2027
Solar + storage project IC-1086, Perry County
Solar + storage
80.0 MWPaused / redesign Perry, ALSoutheast Nov 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)