Interconnection queue in Texas, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,947 MW
Active in queue1,947 MW12 requests
Agreement signed950 MW7 requests
Withdrawn62,021 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Ca-CO-250B
Battery storage
250 MWIn study El Paso, TXWest Jun 2025target 2029
Sf250SB
Solar + storage
250 MWAgreement signed Hudspeth, TXWest Sep 2023target 2028
Co200B
Battery storage
200 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Wi-Al2-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Wi-Al3-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Wi-Al-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2028
Ea150B
Battery storage
150 MWIn study El Paso, TXWest Jun 2025target 2028
Sf150SB
Solar + storage
150 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Ne100B
Battery storage
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
SS100S
Solar
100 MWAgreement signed El Paso, TXWest Sep 2022target 2025
Ne100S
Solar
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
SS50S
Solar
50.0 MWAgreement signed El Paso, TXWest Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)