πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Kentucky, PJM (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown172,881 MW
Active in queue2,881 MW17 requests
Agreement signed0.0 MW0 requests
Withdrawn5450 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-351
Solar
1,000 MWIn study KYPJM Mar 2022target 2027
Solar project AH2-353
Solar
1,000 MWIn study KYPJM Mar 2022target 2028
Battery storage project AH2-125
Battery storage
100 MWIn study KYPJM Feb 2022target 2028
Solar + storage project AI1-180
Solar + storage
100 MWIn study KYPJM Sep 2022target 2027
Solar project AH2-130
Solar
85.0 MWIn study KYPJM Feb 2022target 2026
Solar + storage project AI1-165, Green County
Solar + storage
85.0 MWIn study Green, KYPJM Sep 2022target 2026
Solar + storage project AI1-132, Washington County
Solar + storage
83.0 MWIn study Washington, KYPJM Sep 2022target 2029
Solar + storage project AH2-383, Fleming County
Solar + storage
70.0 MWIn study Fleming, KYPJM Mar 2022target 2027
Solar + storage project AI1-079, Adair County
Solar + storage
64.8 MWIn study Adair, KYPJM Jul 2022target 2026
Solar + storage project AH2-076, Perry County
Solar + storage
52.5 MWIn study Perry, KYPJM Jan 2022target 2023
Solar + storage project AI1-019
Solar + storage
50.0 MWIn study KYPJM Apr 2022target 2026
Solar + storage project AI1-133, Fleming County
Solar + storage
50.0 MWIn study Fleming, KYPJM Sep 2022target 2029
Solar + storage project AI1-159, Montgomery County
Solar + storage
35.0 MWIn study Montgomery, KYPJM Sep 2022target 2028
Solar + storage project AH2-411
Solar + storage
30.0 MWIn study KYPJM Mar 2022target 2025
Solar project AH2-117, Pike County
Solar
30.0 MWIn study Pike, KYPJM Feb 2022target 2026
Solar project AH2-263, Marion County
Solar
25.8 MWIn study Marion, KYPJM Mar 2022target 2026
Solar + storage project AH2-410
Solar + storage
20.0 MWIn study KYPJM Mar 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)