United States › Grid › Interconnection queues › Kentucky
SOLAR + STORAGE · PJMSolar + storage project AI1-159, Montgomery County
Solar + storage project AI1-159, Montgomery County is a 35.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Montgomery County, Kentucky, connecting to EKPC.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-159
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Mount Sterling - Sideview 69 kV
- Location
- Montgomery County, Kentucky
- Technology
- Solar: 35.0 MW · Battery
- Total requested
- 35.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 9 September 2022
- Proposed online date
- December 2028
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Solar project AG2-081, Montgomery CountySolar · 30.0 MW · in study
- Solar project AG1-208, Montgomery CountySolar · 35.0 MW · withdrawn
- Solar project AG1-381, Montgomery CountySolar · 27.0 MW · withdrawn
- Solar project AG2-671, Montgomery CountySolar · 19.9 MW · withdrawn
- Solar project AH1-464, Montgomery CountySolar · 12.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem