Requests shown142,377 MW
Active in queue2,377 MW14 requests
Agreement signed1,512 MW9 requests
Withdrawn399,082 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Livingston Wind
Onshore wind Β· Livingston Wind Project, LLC
255 MWIn study Livingston, ILPJM Sep 2018target 2021
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026
Osagrove Flats Wind
Onshore wind
150 MWAgreement signed Lasalle, ILPJM Jan 2018target 2026
Leaf River Wind
Onshore wind Β· Leaf River Wind, LLC
150 MWIn study Ogle, ILPJM Sep 2018target 2021
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Sep 2018target 2027
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Shady Oaks Wind Power Project
Onshore wind
106 MWAgreement signed Lee, ILPJM Mar 2018target 2027
Broomstick Solar Energy Centergy Center
Solar
50.0 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Staley Solar
Solar
20.0 MWAgreement signed Kankakee, ILPJM Feb 2018target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)