United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Illinois, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown253,379 MW
Active in queue21.8 GW149 requests
Agreement signed3,379 MW25 requests
Withdrawn37457.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Rolling Farms Wind Project
Onshore wind
200 MWAgreement signed Christian, ILPJM Aug 2019target 2029
Osagrove Flats Wind
Onshore wind
150 MWAgreement signed Lasalle, ILPJM Jan 2018target 2026
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Mar 2019target 2027
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Sep 2018target 2027
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Shady Oaks Wind Power Project
Onshore wind
106 MWAgreement signed Lee, ILPJM Mar 2018target 2027
Three Rivers Energy Center
Gas
103 MWAgreement signed Grundy, ILPJM Jul 20172023
Panther Grove 2
Onshore wind
100 MWAgreement signed Woodford, ILPJM Mar 2019target 2027
Red Maple Solar
Solar
94.9 MWAgreement signed Adams, ILPJM Mar 2020target 2028
Zion Energy Center - BESS
Battery storage
50.0 MWAgreement signed Lake, ILPJM Nov 2019target 2027
Twin Groves Storage II
Battery storage
50.0 MWAgreement signed Mclean, ILPJM Mar 2020target 2028
Staley Solar
Solar
50.0 MWAgreement signed Kankakee, ILPJM Mar 2017target 2027
Panther Grove Wind
Onshore wind
50.0 MWAgreement signed Woodford, ILPJM Mar 2019target 2027
Twin Groves Storage I
Battery storage
50.0 MWAgreement signed Mclean, ILPJM Mar 2020target 2028
Rochelle Solar
Solar
40.0 MWAgreement signed Ogle, ILPJM Apr 2017target 2028
Calumet BESS
Battery storage
20.0 MWAgreement signed Cook, ILPJM Oct 2019target 2027
Rochelle Solar
Solar
20.0 MWAgreement signed Ogle, ILPJM Sep 2019target 2028
Kincaid PV
Solar
20.0 MWAgreement signed Christian, ILPJM Oct 2019target 2028
Staley Solar
Solar
20.0 MWAgreement signed Kankakee, ILPJM Feb 2018target 2024
Wilmington Solar Energy Project
Solar + storage
19.9 MWAgreement signed Will, ILPJM Sep 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)