🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in NYISO (New York)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,531324.1 GW
Active in queue27.1 GW190 requests
Agreement signed0.0 MW0 requests
Withdrawn1,531324.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,531 requests · page 1 of 31
ProjectCapacityStatusLocationRegionQueuedOnline
Blue Sky Interconnect 2
Offshore wind · Blue Sky Interconnect, LLC
2,620 MWWithdrawn / abandoned Kings, NYNYISO Mar 2023
Atlantic Shores Offshore Wind Bight 2
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Richmond, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 5
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Richmond, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 4
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Kings, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 1
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Kings, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 3
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Suffolk, NYNYISO Feb 2022
Empire Connection DC
Other · Conjunction, LLC
2,000 MWWithdrawn / abandoned NYNYISO Jun 2003
Nine Mile Point Station Unit #3
Nuclear · UniStar Nuclear Energy
1,660 MWWithdrawn / abandoned Oswego, NYNYISO Feb 2008
OW Ocean Winds East 5
Offshore wind · OW Ocean Winds East, LLC
1,600 MWWithdrawn / abandoned Queens, NYNYISO Jun 2021
OW Ocean Winds East 7
Offshore wind · OW Ocean Winds East
1,600 MWWithdrawn / abandoned Kings, NYNYISO May 2022
OW Ocean Winds East 4
Offshore wind · Bluepoint Wind, LLC.
1,600 MWWithdrawn / abandoned Kings, NYNYISO May 2021
Agr NY-1
Offshore wind · Avangrid Renewables
1,600 MWWithdrawn / abandoned Kings, NYNYISO Feb 2022
Agr NY-2
Offshore wind · Avangrid Renewables
1,600 MWWithdrawn / abandoned Richmond, NYNYISO Feb 2022
EI Steinway 1.1
Onshore wind · Beacon Wind
1,600 MWWithdrawn / abandoned Queens, NYNYISO Sep 2024
OW Ocean Winds East 6
Offshore wind · OW Ocean Winds East, LLC
1,600 MWWithdrawn / abandoned New York, NYNYISO Jun 2021
OW Ocean Winds East 3
Offshore wind · OW Ocean Winds East, LLC
1,600 MWWithdrawn / abandoned Nassau, NYNYISO May 2021
EI Empire ESS II
Wind + storage · Empire Offshore Wind LLC
1,440 MWWithdrawn / abandoned Nassau, NYNYISO May 2021
Vineyard Wind I
Offshore wind · OCS-A 0522, LLC
1,403 MWWithdrawn / abandoned Nassau, NYNYISO Apr 2020
Vineyard Wind II
Offshore wind · OCS-A 0522, LLC
1,403 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2020
Atlantic Shores Offshore Wind Project 5
Offshore wind · ATLANTIC SHORES OFFSHORE WIND BIGHT LLC
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Atlantic Shores Offshore Wind Project 3
Offshore wind · ATLANTIC SHORES OFFSHORE WIND LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
NY Wind - Pilgrim CSR
Wind + storage · Bay State Wind
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2023
NY Wind - Mott Haven CSR
Wind + storage · Bay State Wind
1,400 MWWithdrawn / abandoned Bronx, NYNYISO Jan 2023
Atlantic Shores Offshore Wind Project 4
Offshore wind · Atlantic Shores Offshore Wind Bight LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
NY Wind - Pilgrim Uprate
Offshore wind · Bay State Wind
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2022
Bluepoint Wind 4
Offshore wind · Bluepoint Wind LLC
1,382 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2023
Community OSW Brooklyn CEH 3
Onshore wind · Community Offshore Wind, LLC
1,365 MWWithdrawn / abandoned Kings, NYNYISO Nov 2023
Vineyard Mid-Atlantic 1
Offshore wind · Vineyard Mid-Atlantic
1,350 MWWithdrawn / abandoned Kings, NYNYISO Aug 2022
New Scotland BESS
Battery storage · Eden Renewables
1,350 MWWithdrawn / abandoned Albany, NYNYISO Nov 2023
New Scotland BES 1 and 2
Battery storage · Eden Renewables
1,350 MWWithdrawn / abandoned Albany, NYNYISO Mar 2023
Vineyard Northeast 1
Offshore wind · Vineyard Northeast
1,350 MWWithdrawn / abandoned Kings, NYNYISO Sep 2022
New Scotland BESS
Battery storage · Eden DevCo
1,350 MWWithdrawn / abandoned Albany, NYNYISO Feb 2024
New Scotland BESS
Battery storage · New Scotland BESS
1,350 MWWithdrawn / abandoned Albany, NYNYISO Aug 2024
Vineyard Northeast 2
Offshore wind · Vineyard Northeast LLC
1,345 MWWithdrawn / abandoned Kings, NYNYISO Oct 2022
Vineyard Mid-Atlantic 3
Offshore wind · Vineyard Mid-Atlantic LLC
1,330 MWWithdrawn / abandoned Nassau, NYNYISO Nov 2022
Vineyard Mid-Atlantic 2
Offshore wind · Vineyard Mid-Atlantic
1,330 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2022
NY Wind - New Bridge Road
Offshore wind · Bay State Wind
1,325 MWWithdrawn / abandoned Nassau, NYNYISO Jul 2020
Cosw Bceh
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Bluepoint Wind 2
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Long Island Wind
Offshore wind · Bay State Wind
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Community OSW Barrett 3
Onshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Nassau, NYNYISO Dec 2023
COSW Barrett
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Bluepoint Wind 1
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Sep 2023
Queensboro Renewable Express Circuit A
Onshore wind · Queensboro Development, LLC
1,310 MWWithdrawn / abandoned Queens, NYNYISO Aug 2024
Queensboro Renewable Express Circuit A
Offshore wind · Queensboro Development, LLC
1,310 MWWithdrawn / abandoned Queens, NYNYISO Dec 2022
Attentive Energy 1
Offshore wind · Attentive Energy
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2022
Blue Point Wind 3A
Onshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Richmond, NYNYISO Sep 2023
Bluepoint Wind 2
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Sep 2023
Queensboro B
Onshore wind · Light & Power Development
1,310 MWWithdrawn / abandoned Queens, NYNYISO Nov 2023
Attentive Energy 2
Offshore wind · Attentive Energy
1,310 MWWithdrawn / abandoned Kings, NYNYISO Jun 2022
Page 1 of 31

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)