πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,143 MW
Active in queue3,679 MW23 requests
Agreement signed325 MW1 requests
Withdrawn101,143 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2766, Howard County
Battery storage
190 MWWithdrawn / abandoned Howard, INMISO Aug 2023target 2025
Replacing 180MW with BESS of the existing 280 MW Steam; LANSING 4
Other
180 MWWithdrawn / abandoned Allamakee, IAMISO Sep 2023target 2026
Solar project J2393, Coles County
Solar
164 MWWithdrawn / abandoned Coles, ILMISO Aug 2023target 2027
Solar project J2612, Madison County
Solar
150 MWWithdrawn / abandoned Madison, MSMISO Sep 2023target 2026
Solar project J2770, Grant Parish County
Solar
125 MWWithdrawn / abandoned Grant Parish, LAMISO Sep 2023target 2026
Solar project J2721, Panola County
Solar
120 MWWithdrawn / abandoned Panola, MSMISO Oct 2023target 2026
Replacing 100 MW of gas generation with solar generation; Tidelands
Other
100 MWWithdrawn / abandoned MISO Feb 2023target 2024
Battery storage project J1695, Perry County
Battery storage
50.0 MWWithdrawn / abandoned Perry, ILMISO Dec 2023target 2023
Solar + storage project J2780, Pulaski County
Solar + storage
33.0 MWWithdrawn / abandoned Pulaski, INMISO Oct 2023target 2025
Replacing 31 MW of generation with linear generators powered by natural gas; Burlington 3
Gas
31.0 MWWithdrawn / abandoned Des Moines, IAMISO Dec 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)