OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Missouri, MISO (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J3996, St. Charles County Gas |
2,220 MW | In study |
| Solar project E0013, Sullivan County Solar Β· Union Electric Company d/b/a Ameren Missouri |
310 MW | In study |
| Solar project J3957, Sullivan County Solar |
300 MW | In study |
| Battery storage project E0017, Lincoln County Battery storage Β· Union Electric Company d/b/a Ameren Missouri |
258 MW | In study |
| Onshore wind project J3929, Audrain County Onshore wind |
250 MW | In study |
| Solar project J4001, Marion County Solar |
245 MW | In study |
| Surplus; J944 Battery storage |
200 MW | In study |
| Solar + storage project J2238, Maries County Solar + storage |
200 MW | In study |
| Solar + storage project J2265, Bollinger County Solar + storage |
200 MW | In study |
| Solar project J3919, Lincoln County Solar |
200 MW | In study |
| Solar project J3959, Grundy County Solar |
200 MW | In study |
| Solar project J4090, Schuyler County Solar |
200 MW | In study |
| Solar project J2288, Ralls County Solar |
175 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)18 Β· 5,033 MW
- MISO (Midcontinent)13 Β· 4,958 MW
- Southeast (non-ISO utilities)5 Β· 1,920 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)