United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Missouri, MISO (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,898 MW
Active in queue1,898 MW10 requests
Agreement signed0.0 MW0 requests
Withdrawn233,636 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J3199, Adair County
Solar + storage
300 MWIn study Adair, MOMISO Sep 2022target 2026
Other project J2691, Bollinger County
Other
250 MWIn study Bollinger, MOMISO Sep 2022target 2027
Solar project J2050, Macon County
Solar
208 MWIn study Macon, MOMISO Mar 2022target 2024
Solar project J2524, Stoddard County
Solar
200 MWIn study Stoddard, MOMISO Sep 2022target 2026
Solar project J2806, Warren County
Solar
200 MWIn study Warren, MOMISO Sep 2022target 2026
Solar project J1948, Marion County
Solar
195 MWIn study Marion, MOMISO Mar 2022target 2024
Solar project J2155, New Madrid County
Solar
150 MWIn study New Madrid, MOMISO Mar 2022target 2024
Solar + storage project J3229, Maries County
Solar + storage
140 MWIn study Maries, MOMISO Sep 2022target 2026
Solar + storage project J2593, Gasconade County
Solar + storage
140 MWIn study Gasconade, MOMISO Sep 2022target 2026
Solar + storage project J2382, Randolph County
Solar + storage
115 MWIn study Randolph, MOMISO Sep 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)