United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Missouri, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown103,206 MW
Active in queue14.8 GW53 requests
Agreement signed3,206 MW10 requests
Withdrawn9218.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Onshore wind project J1026, Audrain County
Onshore wind
400 MWAgreement signed Audrain, MOMISO Mar 2018target 2023
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Solar project J1145, Callaway County
Solar
250 MWAgreement signed Callaway, MOMISO Mar 2018target 2024
Onshore wind project J476, Atchison County
Onshore wind
246 MWAgreement signed Atchison, MOMISO Sep 2015target 2021
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Solar project J1268, Lincoln County
Solar
150 MWAgreement signed Lincoln, MOMISO Apr 2019target 2023
Solar project J1352, Montgomery County
Solar
100 MWAgreement signed Montgomery, MOMISO Apr 2019target 2024
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)