Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests · page 9 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Flat Creek Solar
Solar · Flat Creek Solar NY LLC
200 MWWithdrawn / abandoned Montgomery, NYNYISO Sep 2024
Solar + storage project J3467, Mclean County
Solar + storage
200 MWWithdrawn / abandoned Mclean, ILMISO Apr 2024target 2027
Battery storage project J3832, Macomb County
Battery storage
200 MWWithdrawn / abandoned Macomb, MIMISO Jul 2024target 2028
Solar project J3612, Sabine Parish County
Solar
200 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Battery storage project J3369, Scott County
Battery storage
200 MWWithdrawn / abandoned Scott, MNMISO Mar 2024target 2028
Battery storage project J3635, Kent County
Battery storage
200 MWWithdrawn / abandoned Kent, MIMISO Apr 2024target 2027
Battery storage project J3220, Ionia County
Battery storage
200 MWWithdrawn / abandoned Ionia, MIMISO Aug 2024target 2026
Solar + storage project LGE-GIS-2024-005, Breckinridge County
Solar + storage
200 MWWithdrawn / abandoned Breckinridge, KYSoutheast May 2024target 2027
Battery storage project 24-255, Yamhill County
Battery storage
200 MWWithdrawn / abandoned Yamhill, ORWest May 2024target 2027
Battery storage project 24-251, Marion County
Battery storage
200 MWWithdrawn / abandoned Marion, ORWest May 2024target 2027
Solar project J3459, Craighead County
Solar
200 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2028
Independence BESS
Battery storage · Independence BESS LLC
200 MWWithdrawn / abandoned Oswego, NYNYISO Sep 2024
Battery storage project J3634, Gratiot County
Battery storage
200 MWWithdrawn / abandoned Gratiot, MIMISO Apr 2024target 2027
Battery storage project C4-062, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest May 2024target 2028
Battery storage project C4-063, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest May 2024target 2028
Solar + storage project PIS064, Yakima County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Yakima, WAWest Jun 2024target 2028
Battery storage project C4-065, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest May 2024target 2028
Battery storage project PIS082, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest Jun 2024target 2028
Gas project C4-031, Millard County
Gas
200 MWWithdrawn / abandoned Millard, UTWest May 2024target 2029
Battery storage project PIS080, Owyhee County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Owyhee, IDWest Jun 2024target 2028
Solar + storage project C4-053, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest May 2024target 2028
Battery storage project C4-050, Sweetwater County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest May 2024target 2028
Battery storage project C4-064, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest May 2024target 2028
Battery storage project PIS085, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest Jun 2024target 2028
Solar + storage project C4-052, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest May 2024target 2028
Battery storage project PIS086, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest Jun 2024target 2028
Solar + storage project PIS070, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Battery storage project C4-061, Owyhee County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Owyhee, IDWest May 2024target 2028
Solar + storage project PIS063, Kittitas County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Kittitas, WAWest Jun 2024target 2028
Battery storage project C4-068, Morrow County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Morrow, ORWest May 2024target 2028
Battery storage project PIS081, Emery County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Emery, UTWest Jun 2024target 2028
Battery storage project PIS083, Sweetwater County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2024target 2028
Solar + storage project PIS072, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Solar + storage project PIS071, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Solar + storage project C4-076, Yakima County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Yakima, WAWest May 2024target 2028
Battery storage project C4-049, Carbon County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2028
Solar + storage project C4-075, Kittitas County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Kittitas, WAWest May 2024target 2028
Solar + storage project C4-051, Tooele County
Solar + storage · PacifiCorp
200 MWWithdrawn / abandoned Tooele, UTWest May 2024target 2028
Battery storage project PIS079, Morrow County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Morrow, ORWest Jun 2024target 2028
Battery storage project PIS084, Carbon County
Battery storage · PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest Jun 2024target 2028
Ditch Creek
Solar + storage · Ditch Creek Solar LLC
200 MWWithdrawn / abandoned Madison, NYNYISO Oct 2024
BPP NY Somerset BESS I LLC
Battery storage · BPP NY Somerset BESS I LLC
200 MWWithdrawn / abandoned Niagara, NYNYISO Aug 2024
North Creek
Solar + storage · North Creek Solar LLC
200 MWWithdrawn / abandoned Oneida, NYNYISO Oct 2024
Battery storage project GEN-2024-048, Ford County
Battery storage
199 MWWithdrawn / abandoned Ford, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-049, Ford County
Battery storage
199 MWWithdrawn / abandoned Ford, KSSPP Oct 2024target 2028
Battery storage project C4-081, Salt Lake County
Battery storage
199 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
ELP Clay Storage
Battery storage · ELP Clay Storage LLC
199 MWWithdrawn / abandoned Onondaga, NYNYISO Aug 2024
Solar + storage project C4-013, Franklin County
Solar + storage
199 MWWithdrawn / abandoned Franklin, WAWest May 2024target 2027
Solar + storage project C4-025, Natrona County
Solar + storage
199 MWWithdrawn / abandoned Natrona, WYWest May 2024target 2028
Solar project J3717, Yalobusha County
Solar
199 MWWithdrawn / abandoned Yalobusha, MSMISO Apr 2024target 2028
Page 9 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)