United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 9 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project G06_W47, Allegheny County
Gas
500 MWWithdrawn / abandoned Allegheny, PAPJM Feb 2001target 2005
Hydro project AE2-135, Schuylkill County
Hydro
500 MWWithdrawn / abandoned Schuylkill, PAPJM Mar 2019target 2022
Solar + storage project AE1-215, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Gas project AB1-108, Lackawanna County
Gas
485 MWWithdrawn / abandoned Lackawanna, PAPJM Oct 2015target 2019
Coal project R44, Henderson County
Coal
485 MWWithdrawn / abandoned Henderson, KYPJM Nov 2006target 2011
Gas project AD2-182, Marshall County
Gas
482 MWWithdrawn / abandoned Marshall, WVPJM Mar 2018target 2022
Gas project S122, Cumberland County
Gas
478 MWWithdrawn / abandoned Cumberland, NJPJM Jul 2007target 2010
Other project Z1-084
Other
475 MWWithdrawn / abandoned PJM Oct 2013
Gas project A43, Northampton County
Gas
472 MWWithdrawn / abandoned Northampton, PAPJM Jan 1999
Gas project G37, Monmouth County
Gas
471 MWWithdrawn / abandoned Monmouth, NJPJM Jul 2001
Gas project Z1-047, Mifflin County
Gas
464 MWWithdrawn / abandoned Mifflin, PAPJM Aug 2013target 2017
Gas project Z1-048, Marion County
Gas
464 MWWithdrawn / abandoned Marion, WVPJM Aug 2013target 2017
Gas project Z1-030, Lucas County
Gas
464 MWWithdrawn / abandoned Lucas, OHPJM Jun 2013target 2017
Gas project Z1-049, Pleasants County
Gas
464 MWWithdrawn / abandoned Pleasants, WVPJM Aug 2013target 2017
Renovo Energy Center
Gas
463 MWWithdrawn / abandoned Clinton, PAPJM Oct 2014target 2025
Gas project Y1-036, Lake County
Gas
462 MWWithdrawn / abandoned Lake, OHPJM Mar 2012target 2017
Gas project Y1-035, Lake County
Gas
462 MWWithdrawn / abandoned Lake, OHPJM Mar 2012target 2017
Gas project Y3-042, Washington County
Gas
460 MWWithdrawn / abandoned Washington, PAPJM Feb 2013target 2015
Offshore wind project AG2-108, Sussex County
Offshore wind
460 MWWithdrawn / abandoned Sussex, DEPJM Jan 2021target 2026
Gas project Q86, Hudson County
Gas
455 MWWithdrawn / abandoned Hudson, NJPJM Jul 2006target 2010
Gas project Z2-041, Mchenry County
Gas
455 MWWithdrawn / abandoned Mchenry, ILPJM Feb 2014target 2018
Gas project AH1-753, Marshall County
Gas · Calpine Mid-Atlantic Development, LLC
455 MWWithdrawn / abandoned Marshall, WVPJM target 2019
B.L. England Station
Gas
452 MWWithdrawn / abandoned Cape May, NJPJM Feb 2012target 2021
Garrison Energy Center
Gas
451 MWWithdrawn / abandoned New Castle, DEPJM Feb 2015target 2024
Offshore wind project R37, Sussex County
Offshore wind
450 MWWithdrawn / abandoned Sussex, DEPJM Nov 2006target 2014
Gas project A58, Prince George's County
Gas
450 MWWithdrawn / abandoned Prince George's, MDPJM Mar 1999
Other project AI1-202, Grant County
Other
450 MWWithdrawn / abandoned Grant, WVPJM Sep 2022target 2026
Gas project G02_W43, Upshur County
Gas
450 MWWithdrawn / abandoned Upshur, WVPJM Feb 2001target 2005
Gas project A61, New Castle County
Gas
450 MWWithdrawn / abandoned New Castle, DEPJM Mar 1999
Bluewater Wind - Bethany
Offshore wind
450 MWWithdrawn / abandoned DEPJM Nov 2006target 2018
Onshore wind project S31, White County
Onshore wind
450 MWWithdrawn / abandoned White, INPJM May 2007target 2009
Gas project I11, Atlantic County
Gas
450 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2002target 2006
Solar + storage project AH1-645, Isle Of Wight County
Solar + storage
450 MWWithdrawn / abandoned Isle Of Wight, VAPJM Sep 2021target 2025
Onshore wind project W2-046, Livingston County
Onshore wind
450 MWWithdrawn / abandoned Livingston, ILPJM Jun 2010target 2013
Gas project A42, Monmouth County
Gas
449 MWWithdrawn / abandoned Monmouth, NJPJM Jan 1999
Offshore wind project AG2-347, Sussex County
Offshore wind · US Wind, Inc
449 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2025
Offshore wind project AE2-023, Atlantic County
Offshore wind
445 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2024
Offshore wind project AE2-025, Ocean County
Offshore wind
445 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2026
Offshore wind project AG1-087, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2026
Gas project T123, Gloucester County
Gas
440 MWWithdrawn / abandoned Gloucester, NJPJM Jan 2008target 2012
Offshore wind project AF2-193, Sussex County
Offshore wind · GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Gateway Energy Center
Gas
440 MWWithdrawn / abandoned Middlesex, NJPJM Sep 2006target 2020
Offshore wind project AG2-342, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2026
Offshore wind project AF2-194, Sussex County
Offshore wind · GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Gas project X3-088, Montgomery County
Gas
440 MWWithdrawn / abandoned Montgomery, MDPJM Oct 2011target 2016
Gas project D05_W17, Garrett County
Gas
432 MWWithdrawn / abandoned Garrett, MDPJM Jun 2000target 2004
South Bend Generating Station
Gas
410 MWWithdrawn / abandoned Armstrong, PAPJM Mar 2018target 2023
Onshore wind project AD1-104, Van Wert County
Onshore wind
403 MWWithdrawn / abandoned Van Wert, OHPJM Sep 2017target 2021
Gas project W3-172, New Castle County
Gas
402 MWWithdrawn / abandoned New Castle, DEPJM Oct 2010target 2013
Gas project A44, Indiana County
Gas
402 MWWithdrawn / abandoned Indiana, PAPJM Jan 1999
Page 9 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)