United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Illinois — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35863.7 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

358 requests · page 8 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AI2-403, Dekalb County
Solar
19.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project AI1-173, Stephenson County
Solar
16.0 MWIn study Stephenson, ILPJM Sep 2022target 2027
Solar project AI1-077, Mchenry County
Solar
15.8 MWIn study Mchenry, ILPJM Jul 2022target 2025
Onshore wind project J2189, Mcdonough County
Onshore wind
15.6 MWIn study Mcdonough, ILMISO Aug 2021target 2019
Battery storage project AH2-205, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Aurora Battery Storage
Battery storage
10.0 MWPaused / redesign Will, ILPJM Oct 2020target 2028
Battery storage project AH2-206, Cook County
Battery storage
10.0 MWIn study Cook, ILPJM Mar 2022target 2026
Gas project AH1-567, Will County
Gas · University Park Energy, LLC
5.0 MWIn study Will, ILPJM Mar 2025target 2025
Page 8 of 8

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)