🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in West (non-ISO utilities) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,496455.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,496 requests · page 7 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company 218, Clark County
Solar + storage
460 MWPaused / redesign Clark, NVWest Mar 2023target 2029
Gas project 2023-G13, La Paz County
Gas
453 MWIn study La Paz, AZWest Oct 2023target 2027
Gas project 08-030, Morrow County
Gas
450 MWPaused / redesign Morrow, ORWest May 2008target 2013
Solar + storage project Q44, Millard County
Solar + storage · Intermountain Power Agency
450 MWIn study Millard, UTWest Sep 2013target 2018
Gas project 08-031, Columbia County
Gas
450 MWPaused / redesign Columbia, ORWest May 2008target 2014
Battery storage project 310, Meagher County
Battery storage
450 MWPaused / redesign Meagher, MTWest Dec 2016target 2023
Solar + storage project Q337, Yavapai County
Solar + storage
450 MWIn study Yavapai, AZWest Mar 2020target 2027
Solar + storage project Q352, Navajo County
Solar + storage
450 MWIn study Navajo, AZWest Sep 2020target 2023
Battery storage project C002, Meagher County
Battery storage
450 MWPaused / redesign Meagher, MTWest Dec 2016target 2020
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Other project Q567, Maricopa County
Other
450 MWIn study Maricopa, AZWest May 2024target 2028
Solar + storage project Company OF, Lander County
Solar + storage
450 MWPaused / redesign Lander, NVWest Jan 2023target 2028
Solar project G0712, Sherman County
Solar
448 MWIn study Sherman, ORWest Nov 2021target 2025
Gas project Q40, Maricopa County
Gas
425 MWIn study Maricopa, AZWest Aug 2023target 2028
Solar + storage project Company 191, Clark County
Solar + storage
425 MWPaused / redesign Clark, NVWest Aug 2020target 2022
Other project Q560, Maricopa County
Other
425 MWIn study Maricopa, AZWest May 2024target 2028
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Solar + storage project G0844, Klickitat County
Solar + storage
420 MWIn study Klickitat, WAWest Feb 2023target 2026
Wind + storage project G0728, Sherman County
Wind + storage
420 MWIn study Sherman, ORWest Feb 2022target 2026
Battery storage project Q2511, Maricopa County
Battery storage
419 MWIn study Maricopa, AZWest Feb 2025target 2029
Battery storage project PIS107, Klamath County
Battery storage
416 MWIn study Klamath, ORWest Dec 2025target 2022
Battery storage project 687, Klamath County
Battery storage · Swan Lake North Hydro, LLC
416 MWIn study Klamath, ORWest Jul 2015target 2031
Gas project CSUT-2025-7, El Paso County
Gas
412 MWIn study El Paso, COWest Mar 2025target 2028
Battery storage project Q2413, Pinal County
Battery storage
409 MWIn study Pinal, AZWest Feb 2024target 2027
Onshore wind project 09-035, Gilliam County
Onshore wind
401 MWPaused / redesign Gilliam, ORWest Jul 2009target 2013
Onshore wind project T2-057, Carbon County
Onshore wind
400 MWIn study Carbon, WYWest Sep 2025target 2029
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Other project Q581, Maricopa County
Other
400 MWIn study Maricopa, AZWest May 2025target 2031
Solar + storage project 2023-G1
Solar + storage
400 MWIn study West Oct 2022target 2025
Solar + storage project G0744, Grant County
Solar + storage
400 MWIn study Grant, WAWest May 2022target 2026
Other project SC1Q31, Sacramento County
Other
400 MWIn study Sacramento, CAWest Jul 2025target 2032
Solar project G1035, Douglas County
Solar
400 MWIn study Douglas, WAWest Nov 2023target 2028
Battery storage project Q116, Clark County
Battery storage
400 MWIn study Clark, NVWest Nov 2025target 2032
Solar + storage project C1-44, Lake County
Solar + storage · Archway Solar Energy LLC
400 MWPaused / redesign Lake, ORWest May 2021target 2025
Solar + storage project Q537, Pinal County
Solar + storage
400 MWIn study Pinal, AZWest Sep 2023target 2027
Onshore wind project GI-2023-14, Morgan County
Onshore wind
400 MWPaused / redesign Morgan, COWest May 2023target 2026
Battery storage project 25-00384, Clark County
Battery storage
400 MWIn study Clark, NVWest Jul 2025target 2029
Solar + storage project GI-2024-05, Pueblo County
Solar + storage
400 MWIn study Pueblo, COWest Apr 2024target 2028
Battery storage project IA-PNM-2025-09, Valencia County
Battery storage
400 MWIn study Valencia, NMWest Mar 2025target 2029
Onshore wind project 367, Rosebud County
Onshore wind
400 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Gas project 5RSC-2024-02, Weld County
Gas
400 MWIn study Weld, COWest Jan 2024target 2027
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Wind + storage project Company MX, Lyon County
Wind + storage
400 MWPaused / redesign Lyon, NVWest Mar 2022target 2027
Battery storage project 23-221, Washington County
Battery storage
400 MWIn study Washington, ORWest Mar 2023target 2027
Solar + storage project T2-085, Utah County
Solar + storage
400 MWIn study Utah, UTWest Sep 2025target 2030
Other project G0895, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0893, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project Q589, Pinal County
Other
400 MWIn study Pinal, AZWest May 2025target 2030
Onshore wind project 2025-G7
Onshore wind
400 MWIn study West Nov 2025target 2029
Page 7 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)