United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Illinois, MISO — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown27452.8 GW
Active in queue52.8 GW274 requests
Agreement signed4,050 MW26 requests
Withdrawn29657.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

274 requests · page 6 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2552, Rock Island County
Battery storage
80.0 MWIn study Rock Island, ILMISO Sep 2022target 2026
Solar project J1475, Clark County
Solar
75.0 MWAgreement signed Clark, ILMISO Apr 20192024
Solar project J1180, Clark County
Solar
75.0 MWUnder construction Clark, ILMISO Mar 20182024
Solar project J1102, Logan County
Solar
70.0 MWUnder construction Logan, ILMISO Mar 20182022
Solar + storage project J1202, Randolph County
Solar + storage
68.4 MWAgreement signed Randolph, ILMISO Apr 2019target 2024
Onshore wind project J3976, Fayette County
Onshore wind
66.8 MWIn study Fayette, ILMISO Mar 2025target 2028
Battery storage project J2376, Shelby County
Battery storage
60.0 MWIn study Shelby, ILMISO Sep 2022target 2024
Solar + storage project J1198, Jasper County
Solar + storage
51.8 MWAgreement signed Jasper, ILMISO Apr 2019target 2023
Battery storage project J2974, Adams County
Battery storage
50.0 MWIn study Adams, ILMISO Sep 2022target 2026
Battery storage project J3892, Sangamon County
Battery storage
50.0 MWIn study Sangamon, ILMISO Jan 2025target 2028
Battery storage project J2159, Clark County
Battery storage
50.0 MWIn study Clark, ILMISO Aug 2021target 2024
Onshore wind project J2312, Putnam County
Onshore wind
47.9 MWIn study Putnam, ILMISO Oct 2024target 2024
Battery storage project J1882, Tazewell County
Battery storage
45.0 MWIn study Tazewell, ILMISO Mar 2022target 2024
Solar + storage project J1201, Montgomery County
Solar + storage
44.2 MWAgreement signed Montgomery, ILMISO Apr 2019target 2024
Surplus; J1102
Other
40.0 MWIn study Logan, ILMISO Oct 2023target 2025
Solar project J3818, Shelby County
Solar
40.0 MWIn study Shelby, ILMISO Jun 2024target 2028
Solar project J3188, Marshall County
Solar
35.0 MWIn study Marshall, ILMISO Sep 2022target 2023
Solar project J2982, Warren County
Solar
35.0 MWIn study Warren, ILMISO Sep 2022target 2023
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Solar + storage project J1200, Putnam County
Solar + storage
24.2 MWAgreement signed Putnam, ILMISO Apr 2019target 2024
Solar project J3993, Wayne County
Solar
21.4 MWIn study Wayne, ILMISO Apr 2025target 2027
Nuclear project J4010, Dewitt County
Nuclear
21.0 MWIn study Dewitt, ILMISO Apr 2025target 2027
Solar + storage project J1199, Fulton County
Solar + storage
20.0 MWAgreement signed Fulton, ILMISO Apr 2019target 2023
Onshore wind project J2189, Mcdonough County
Onshore wind
15.6 MWIn study Mcdonough, ILMISO Aug 2021target 2019
Page 6 of 6

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20162025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)