🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 56

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 56 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Richfield Solar and Storage
Battery storage
20.0 MWWithdrawn / abandoned Dorchester, MDPJM Aug 2018target 2024
Solar project AF1-149, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2021
Solar project AG1-074, Caroline County
Solar
20.0 MWWithdrawn / abandoned Caroline, VAPJM Jul 2020target 2022
South Point
Other
20.0 MWWithdrawn / abandoned Lawrence, OHPJM Nov 2005target 2012
Solar project W3-082, Cape May County
Solar
20.0 MWWithdrawn / abandoned Cape May, NJPJM Sep 2010target 2011
Solar project AF1-154, Dauphin County
Solar
20.0 MWWithdrawn / abandoned Dauphin, PAPJM Sep 2019target 2022
Crawford Solar III
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2025
Solar project AH1-204, Somerset County
Solar
20.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2021target 2023
Solar project AE2-127, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Feb 2019target 2021
Solar project W1-068, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Apr 2010target 2011
Solar project AC2-020, Ross County
Solar
20.0 MWWithdrawn / abandoned Ross, OHPJM Jan 2017target 2019
Solar project AB2-143, Kent County
Solar
20.0 MWWithdrawn / abandoned Kent, MDPJM Apr 2016target 2018
Battery storage project AF2-009, York County
Battery storage
20.0 MWWithdrawn / abandoned York, PAPJM Oct 2019target 2021
Solar project AC2-147, Ogle County
Solar
20.0 MWWithdrawn / abandoned Ogle, ILPJM Mar 2017target 2019
Solar project AF2-345, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2023
Scarecrow Solar
Solar
20.0 MWWithdrawn / abandoned Huntingdon, PAPJM Sep 2020target 2027
Solar + storage project AG1-272, Charlotte County
Solar + storage · CV-Tollhouse LLC
20.0 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2022
Solar project AA2-154, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Apr 2015target 2015
Battery storage project AA2-106, Jay County
Battery storage
20.0 MWWithdrawn / abandoned Jay, INPJM Apr 2015target 2018
Bear Creek Energy Storage Facility
Battery storage
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Oct 2015target 2022
Solar project W3-031, Burlington County
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Aug 2010target 2012
Solar project AC2-151, Grundy County
Solar
20.0 MWWithdrawn / abandoned Grundy, ILPJM Mar 2017target 2019
Long Bridge
Solar
20.0 MWWithdrawn / abandoned Venango, PAPJM Mar 2020target 2026
Windmill Road
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Jan 2019target 2023
Solar project AH1-172, Carroll County
Solar
20.0 MWWithdrawn / abandoned Carroll, VAPJM Aug 2021target 2022
EL-Mefferts Run
Solar
20.0 MWWithdrawn / abandoned Elk, PAPJM Sep 2019target 2026
Solar project AD2-186, City Of Chesapeake County
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Mar 2018target 2019
Solar project V4-029, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2011
Onshore wind project P17, Lee County
Onshore wind
20.0 MWWithdrawn / abandoned Lee, ILPJM Oct 2005target 2006
Solar project X3-009, Dorchester County
Solar
20.0 MWWithdrawn / abandoned Dorchester, MDPJM Aug 2011target 2017
DW-Lew Jones Solar
Solar · DW-Lew Jones LLC
20.0 MWWithdrawn / abandoned Dinwiddie, VAPJM Sep 2020target 2022
Solar + storage project AG1-384, Charlotte County
Solar + storage · CV-Tollhouse LLC
20.0 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2022
Battery storage project AA1-115, Blair County
Battery storage
20.0 MWWithdrawn / abandoned Blair, PAPJM Oct 2014target 2016
Solar + storage project AH1-419, Susquehanna County
Solar + storage
20.0 MWWithdrawn / abandoned Susquehanna, PAPJM Sep 2021target 2025
Solar project AF1-132, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2021
Other project Q64, City Of Portsmouth County
Other
20.0 MWWithdrawn / abandoned City Of Portsmouth, VAPJM Jul 2006target 2007
Solar project AC2-135, Clarke County
Solar
20.0 MWWithdrawn / abandoned Clarke, VAPJM Mar 2017target 2018
Solar project AB2-063, Queen Anne's County
Solar
20.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Mar 2016target 2018
Surry Solar Center
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM May 2019target 2023
Solar project AE2-116, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Feb 2019target 2021
Solar project AG2-056, Frederick County
Solar
20.0 MWWithdrawn / abandoned Frederick, VAPJM Dec 2020target 2022
Solar project AG1-310, Halifax County
Solar
20.0 MWWithdrawn / abandoned Halifax, VAPJM Sep 2020target 2022
Offshore wind project U2-044, Cape May County
Offshore wind
20.0 MWWithdrawn / abandoned Cape May, NJPJM Jun 2008target 2011
Solar project W3-068, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Sep 2010target 2012
Tolna Energy Center
Solar + storage
20.0 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2028
Solar + storage project AG1-510, Warren County
Solar + storage
20.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2020target 2024
Solar project AH2-136, Essex County
Solar
20.0 MWWithdrawn / abandoned Essex, VAPJM Feb 2022target 2024
Solar project AB2-052, Culpeper County
Solar
20.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2016target 2017
Solar project AG1-519, Louisa County
Solar
20.0 MWWithdrawn / abandoned Louisa, VAPJM Sep 2020target 2022
Solar project AF1-171, Crawford County
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2023
Page 56 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)