Solar project W3-031, Burlington County

Solar project W3-031, Burlington County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2010 (completed)
  2. Withdrawn / abandonedOct 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W3-031
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Medford 69kV
Location
Burlington County, New Jersey
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 August 2010
Proposed online date
February 2012
Withdrawn
October 2010

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem