πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2021 requests) β€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22868.8 GW
Active in queue68.8 GW228 requests
Agreement signed11.7 GW55 requests
Withdrawn33978.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

228 requests Β· page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G0708, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Battery storage project G0707, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Solar + storage project Company 193, Clark County
Solar + storage
57.0 MWAgreement signed Clark, NVWest Mar 2021target 2026
Zinnia Storage
Battery storage
50.0 MWAgreement signed Bernalillo, NMWest Jun 2021target 2024
Solar + storage project 417, Wheatland County
Solar + storage
50.0 MWIn study Wheatland, MTWest Nov 2021target 2022
Belen Energy
Battery storage
49.5 MWIn study Valencia, NMWest Jul 2021target 2025
Gas project GI-2021-2, Weld County
Gas
49.0 MWAgreement signed Weld, COWest Mar 2021target 2022
Solar + storage project C1-10, Emery County
Solar + storage Β· Emery Bull Creek Energy, LLC
45.0 MWPaused / redesign Emery, UTWest Apr 2021target 2029
Solar + storage project GI-2021-4, Conejos County
Solar + storage
42.0 MWPaused / redesign Conejos, COWest Mar 2021target 2024
Battery storage project G0709, Gilliam County
Battery storage
41.0 MWIn study Gilliam, ORWest Oct 2021target 2023
Geothermal project Company LT, Lander County
Geothermal
40.0 MWAgreement signed Lander, NVWest Sep 2021target 2026
Geothermal project Company KY, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Mar 2021target 2027
Geothermal project Company KZ, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Mar 2021target 2027
Gas project GI-2021-3, Weld County
Gas
35.0 MWAgreement signed Weld, COWest Mar 2021target 2021
Gas project Q81, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Jun 2021target 2025
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Other project GI-2021-144, Imperial County
Other
28.0 MWIn study Imperial, CAWest Mar 2021target 2028
Geothermal project Company MM, Esmeralda County
Geothermal
19.8 MWAgreement signed Esmeralda, NVWest Dec 2021target 2025
Onshore wind project G0721, Benton County
Onshore wind
13.6 MWIn study Benton, WAWest Dec 2021target 2024
Solar project G0689, Franklin County
Solar
13.3 MWIn study Franklin, WAWest Sep 2021target 2023
Wind + storage project C1-04, Salt Lake County
Wind + storage
6.0 MWIn study Salt Lake, UTWest Apr 2021target 2023
Other project Q394, Maricopa County
Other
5.0 MWIn study Maricopa, AZWest Mar 2021target 2021
Solar project SGI-PNM-2021-14, Otero County
Solar
5.0 MWIn study Otero, NMWest Apr 2021target 2022
Battery storage project C1-15, Klamath County
Battery storage Β· PacifiCorp
2.3 MWAgreement signed Klamath, ORWest May 2021target 2024
Onshore wind project C1-58, Salt Lake County
Onshore wind
2.0 MWIn study Salt Lake, UTWest May 2021target 2023
Other project G0710, Flathead County
Other
1.6 MWIn study Flathead, MTWest Nov 2021target 2022
Other project Company MN, Lyon County
Other
1.3 MWAgreement signed Lyon, NVWest Dec 2021target 2022
Solar + storage project 120, Spokane County
Solar + storage
1.0 MWIn study Spokane, WAWest Aug 2021target 2022
Page 5 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)