United States › Grid › Interconnection queues › New Mexico

BATTERY STORAGE · WEST

Belen Energy

Belen Energy is a 49.5 MW battery storage request in interconnection study in the West interconnection queue, in Valencia County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusIn planning
  1. PlanningQueued Jul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IA-PNM-2021-17
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Belen Switching Station
Location
Valencia County, New Mexico
Technology
Battery: 49.5 MW
Total requested
49.5 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
12 July 2021
Proposed online date
July 2025

Location

Marker shows the centre of Valencia County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Valencia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem