United States › Grid › Interconnection queues › Georgia

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Georgia — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown510106.6 GW
Active in queue46.5 GW204 requests
Agreement signed16.6 GW57 requests
Withdrawn510106.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

510 requests · page 4 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1190, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, GASoutheast Oct 2023target 2028
Battery storage project IC-1119, Bartow County
Battery storage
200 MWWithdrawn / abandoned Bartow, GASoutheast Feb 2023
Solar project IC-472, Dougherty County
Solar
200 MWWithdrawn / abandoned Dougherty, GASoutheast Jul 2016
Battery storage project IC-821, Clayton County
Battery storage
200 MWWithdrawn / abandoned Clayton, GASoutheast Oct 2019target 2022
Solar + storage project IC-833, Decatur County
Solar + storage
200 MWWithdrawn / abandoned Decatur, GASoutheast Oct 2019
Battery storage project IC-830, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Oct 2019
Solar project IC-1193, Hancock County
Solar
200 MWWithdrawn / abandoned Hancock, GASoutheast Oct 2023target 2028
Solar + storage project IC-965, Mitchell County
Solar + storage
200 MWWithdrawn / abandoned Mitchell, GASoutheast Jun 2021target 2024
Solar + storage project IC-963, Coffee County
Solar + storage
200 MWWithdrawn / abandoned Coffee, GASoutheast Jun 2021
Battery storage project 25-IC-AO, Warren County
Battery storage
200 MWWithdrawn / abandoned Warren, GASoutheast
Battery storage project IC-1275, Mitchell County
Battery storage
200 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2024
Solar + storage project IC-901, Glynn County
Solar + storage
200 MWWithdrawn / abandoned Glynn, GASoutheast Aug 2020target 2023
Solar project IC-1191, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, GASoutheast Oct 2023target 2028
Battery storage project IC-819, Douglas County
Battery storage
200 MWWithdrawn / abandoned Douglas, GASoutheast Oct 2019target 2022
Solar project IC-1194, Hart County
Solar
200 MWWithdrawn / abandoned Hart, GASoutheast Oct 2023target 2028
Solar project IC-701, Miller County
Solar
200 MWWithdrawn / abandoned Miller, GASoutheast May 2018
Battery storage project 25-IC-AJ, Charlton County
Battery storage
199 MWWithdrawn / abandoned Charlton, GASoutheast
Battery storage project 25-IC-AS, Hart County
Battery storage
199 MWWithdrawn / abandoned Hart, GASoutheast
Other project 25-IC-BF, Miller County
Other
199 MWWithdrawn / abandoned Miller, GASoutheast
Solar project 25-IC-1363, Evans County
Solar
195 MWWithdrawn / abandoned Evans, GASoutheast Apr 2025
Gas project IC-035, Clarke County
Gas
185 MWWithdrawn / abandoned Clarke, GASoutheast
Gas project IC-034, Clarke County
Gas
185 MWWithdrawn / abandoned Clarke, GASoutheast
Solar + storage project IC-978, Sumter County
Solar + storage
180 MWWithdrawn / abandoned Sumter, GASoutheast Aug 2021
Solar project IC-540, Dooly County
Solar
180 MWWithdrawn / abandoned Dooly, GASoutheast Nov 2016
Solar project IC-587, Hancock County
Solar
176 MWWithdrawn / abandoned Hancock, GASoutheast Jan 2017
Solar project 25-IC-1364, Burke County
Solar
175 MWWithdrawn / abandoned Burke, GASoutheast Apr 2025
Solar project IC-1240, Putnam County
Solar
175 MWWithdrawn / abandoned Putnam, GASoutheast Jan 2024
Battery storage project IC-1143, Floyd County
Battery storage
175 MWWithdrawn / abandoned Floyd, GASoutheast May 2023
Solar + storage project IC-847, Brooks County
Solar + storage
175 MWWithdrawn / abandoned Brooks, GASoutheast Feb 2020target 2023
Solar project IC-1138, Monroe County
Solar
170 MWWithdrawn / abandoned Monroe, GASoutheast May 2023
Solar project IC-476, Turner County
Solar
170 MWWithdrawn / abandoned Turner, GASoutheast Aug 2016
Solar project IC-753, Turner County
Solar
170 MWWithdrawn / abandoned Turner, GASoutheast Nov 2018
Solar project IC-618, Mitchell County
Solar
167 MWWithdrawn / abandoned Mitchell, GASoutheast Apr 2017
Solar project IC-946, Macon County
Solar
165 MWWithdrawn / abandoned Macon, GASoutheast Apr 2021
Solar project IC-457, Tift County
Solar
165 MWWithdrawn / abandoned Tift, GASoutheast May 2016
Solar + storage project IC-843, Ware County
Solar + storage
163 MWWithdrawn / abandoned Ware, GASoutheast Dec 2019target 2022
Solar project 25-IC-AR, Ware County
Solar
160 MWWithdrawn / abandoned Ware, GASoutheast
Solar project IC-583, Crawford County
Solar
160 MWWithdrawn / abandoned Crawford, GASoutheast Jan 2017
Solar project IC-665, Mitchell County
Solar
155 MWWithdrawn / abandoned Mitchell, GASoutheast Dec 2017
Solar project IC-640, Turner County
Solar
155 MWWithdrawn / abandoned Turner, GASoutheast May 2017
Solar + storage project IC-1274, Mitchell County
Solar + storage
155 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2024
Solar project IC-749, Brantley County
Solar
153 MWWithdrawn / abandoned Brantley, GASoutheast Oct 2018
Solar project IC-445, Sumter County
Solar
152 MWWithdrawn / abandoned Sumter, GASoutheast Mar 2016
Solar project IC-447, Sumter County
Solar
152 MWWithdrawn / abandoned Sumter, GASoutheast Mar 2016
Solar project IC-446, Sumter County
Solar
152 MWWithdrawn / abandoned Sumter, GASoutheast Mar 2016
Solar project IC-374, Putnam County
Solar
151 MWWithdrawn / abandoned Putnam, GASoutheast Apr 2014
Battery storage project IC-1129, Gilmer County
Battery storage
150 MWWithdrawn / abandoned Gilmer, GASoutheast Mar 2023
Solar + storage project 25-IC-AE, Bleckley County
Solar + storage
150 MWWithdrawn / abandoned Bleckley, GASoutheast
Solar project IC-779, Burke County
Solar
150 MWWithdrawn / abandoned Burke, GASoutheast Feb 2019
Solar project IC-867, Terrell County
Solar
150 MWWithdrawn / abandoned Terrell, GASoutheast May 2020
Page 4 of 11

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)