Interconnection queue in Southeast (non-ISO utilities) (2025 requests) β€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26442.0 GW
Active in queue42.0 GW264 requests
Agreement signed92.8 MW3 requests
Withdrawn448,611 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

264 requests Β· page 4 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 25-IC-1357, Monroe County
Solar
71.0 MWIn study Monroe, ALSoutheast Apr 2025target 2029
Other project PP00036, Robeson County
Other
70.0 MWIn study Robeson, NCSoutheast Jul 2025target 2028
Other project PP00045, Lenoir County
Other
70.0 MWIn study Lenoir, NCSoutheast Aug 2025target 2029
Solar project 25RSC-003, Mcminn County
Solar
68.0 MWIn study Mcminn, TNSoutheast Jul 2025target 2031
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Nuclear project 25-IC-1302, Appling County
Nuclear
65.0 MWIn study Appling, GASoutheast Mar 2025target 2031
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
SR Millen
Solar
65.0 MWIn study Jenkins, GASoutheast Jan 2025target 2029
Other project PP00029, Marion County
Other
63.9 MWIn study Marion, SCSoutheast Jun 2025target 2027
Solar project 25RSC-006, Mcnairy County
Solar
62.0 MWIn study Mcnairy, TNSoutheast Jul 2025target 2029
Solar project 286, Orangeburg County
Solar
60.0 MWIn study Orangeburg, SCSoutheast May 2025target 2027
Nuclear project 25-IC-1301, Appling County
Nuclear
60.0 MWIn study Appling, GASoutheast Mar 2025target 2030
Solar project PP00010, Lee County
Solar
60.0 MWUnder construction Lee, SCSoutheast Jan 2025target 2028
Solar + storage project 311, Lexington County
Solar + storage
60.0 MWIn study Lexington, SCSoutheast May 2025target 2030
Gas project 296, Colleton County
Gas
55.6 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 295, Colleton County
Gas
55.6 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 298, Colleton County
Gas
55.6 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 288, Chester County
Gas
55.6 MWIn study Chester, SCSoutheast May 2025target 2030
Gas project 305, Aiken County
Gas
55.6 MWIn study Aiken, SCSoutheast May 2025target 2029
Gas project 297, Colleton County
Gas
55.6 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 307, Aiken County
Gas
55.6 MWIn study Aiken, SCSoutheast May 2025target 2029
Gas project 290, Chester County
Gas
55.6 MWIn study Chester, SCSoutheast May 2025target 2030
Gas project 306, Aiken County
Gas
55.6 MWIn study Aiken, SCSoutheast May 2025target 2029
Gas project 304, Aiken County
Gas
55.6 MWIn study Aiken, SCSoutheast May 2025target 2029
Gas project 291, Chester County
Gas
55.6 MWIn study Chester, SCSoutheast May 2025target 2030
Gas project 294, Georgetown County
Gas
55.6 MWIn study Georgetown, SCSoutheast May 2025target 2028
Gas project 293, Georgetown County
Gas
55.6 MWIn study Georgetown, SCSoutheast May 2025target 2028
Gas project 289, Chester County
Gas
55.6 MWIn study Chester, SCSoutheast May 2025target 2030
Battery storage project 313, Williamsburg County
Battery storage
55.0 MWIn study Williamsburg, SCSoutheast Jun 2025target 2029
Nuclear project 25RSC-002, Roane County
Nuclear
50.0 MWIn study Roane, TNSoutheast Jul 2025target 2029
Other project PP00038, Nash County
Other
50.0 MWIn study Nash, NCSoutheast Jul 2025target 2029
Nuclear project 25-IC-1300, Burke County
Nuclear
50.0 MWIn study Burke, GASoutheast Mar 2025target 2031
Nuclear project 25-IC-1307, Houston County
Nuclear
50.0 MWIn study Houston, ALSoutheast Apr 2025target 2031
Nuclear project 25-IC-1298, Burke County
Nuclear
50.0 MWIn study Burke, GASoutheast Mar 2025target 2030
Nuclear project 25-IC-1309, Houston County
Nuclear
50.0 MWIn study Houston, ALSoutheast Apr 2025target 2031
Solar project 977831, Hoke County
Solar
49.9 MWIn study Hoke, NCSoutheast Jun 2025
Other project PP00052, Chesterfield County
Other
48.0 MWIn study Chesterfield, SCSoutheast Sep 2025target 2029
Gas project PP00013, Richmond County
Gas
46.8 MWAgreement signed Richmond, NCSoutheast Apr 2025target 2025
Gas project 25-IC-1286, Effingham County
Gas
35.0 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project PP00014, Richmond County
Gas
35.0 MWIn study Richmond, NCSoutheast Apr 2025target 2026
Gas project 25-IC-1285, Effingham County
Gas
35.0 MWIn study Effingham, GASoutheast Mar 2025target 2028
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Other project PP00054, Darlington County
Other
30.0 MWIn study Darlington, SCSoutheast Oct 2025target 2027
Solar project 287, Fairfield County
Solar
29.7 MWIn study Fairfield, SCSoutheast May 2025target 2027
Gas project PP00012, Wayne County
Gas
26.0 MWAgreement signed Wayne, NCSoutheast Apr 2025target 2025
Other project PP00053, Darlington County
Other
25.0 MWIn study Darlington, SCSoutheast Oct 2025target 2027
Gas project 25-IC-1316, Kemper County
Gas
25.0 MWIn study Kemper, MSSoutheast Apr 2025target 2027
Other project 977788, Columbus County
Other
22.0 MWIn study Columbus, NCSoutheast Jun 2025
Battery storage project 120, Polk County
Battery storage
20.0 MWIn study Polk, FLSoutheast May 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)