United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 38

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 38 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-2022-9, Pueblo County
Solar + storage
199 MWWithdrawn / abandoned Pueblo, COWest Apr 2022target 2024
Solar project C4-090, Bonneville County
Solar
199 MWWithdrawn / abandoned Bonneville, IDWest May 2024target 2028
Battery storage project C4-108, Salt Lake County
Battery storage
199 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2028
Solar + storage project C4-088, Utah County
Solar + storage
199 MWWithdrawn / abandoned Utah, UTWest May 2024target 2027
Onshore wind project GI-2004-12, Elbert County
Onshore wind
199 MWWithdrawn / abandoned Elbert, COWest Nov 2004target 2005
Onshore wind project C4-110, Cowlitz County
Onshore wind
199 MWWithdrawn / abandoned Cowlitz, WAWest May 2024target 2027
Solar + storage project 791, Owyhee County
Solar + storage
199 MWWithdrawn / abandoned Owyhee, IDWest Mar 2025
Solar + storage project C2-118, Natrona County
Solar + storage
199 MWWithdrawn / abandoned Natrona, WYWest May 2022target 2026
Solar + storage project C4-027, San Juan County
Solar + storage
199 MWWithdrawn / abandoned San Juan, UTWest May 2024target 2028
Solar + storage project C4-046, Millard County
Solar + storage
199 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Solar + storage project GI-2023-12, Arapahoe County
Solar + storage
199 MWWithdrawn / abandoned Arapahoe, COWest May 2023target 2026
Solar + storage project GI-2021-14, Adams County
Solar + storage
199 MWWithdrawn / abandoned Adams, COWest Sep 2021target 2025
Solar + storage project C2-31, Linn County
Solar + storage
199 MWWithdrawn / abandoned Linn, ORWest Apr 2022target 2025
Solar + storage project C1-17, Box Elder County
Solar + storage
199 MWWithdrawn / abandoned Box Elder, UTWest May 2021target 2025
Battery storage project GI-2021-16, Arapahoe County
Battery storage
199 MWWithdrawn / abandoned Arapahoe, COWest Sep 2021target 2025
Solar project IA-PNM-2018-08, Torrance County
Solar
199 MWWithdrawn / abandoned Torrance, NMWest Jul 2018target 2022
Solar + storage project C1-21, Caribou County
Solar + storage
199 MWWithdrawn / abandoned Caribou, IDWest May 2021target 2025
AE199SB
Solar + storage
199 MWWithdrawn / abandoned Chaves, NMWest Jun 2025target 2029
Solar + storage project C3-055, Utah County
Solar + storage
199 MWWithdrawn / abandoned Utah, UTWest May 2023target 2027
Solar + storage project GI-2022-6, Arapahoe County
Solar + storage
199 MWWithdrawn / abandoned Arapahoe, COWest Mar 2022target 2025
Solar + storage project C2-116, Carbon County
Solar + storage
199 MWWithdrawn / abandoned Carbon, WYWest May 2022target 2026
Solar + storage project Q529, Maricopa County
Solar + storage
199 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar project GI-2020-06, Adams County
Solar
199 MWWithdrawn / abandoned Adams, COWest Mar 2020target 2022
Solar project C2-111, Natrona County
Solar
199 MWWithdrawn / abandoned Natrona, WYWest May 2022target 2025
Solar + storage project C3-129, San Juan County
Solar + storage
199 MWWithdrawn / abandoned San Juan, UTWest May 2023target 2027
Solar + storage project GI-2022-11, Pueblo County
Solar + storage
199 MWWithdrawn / abandoned Pueblo, COWest Apr 2022target 2025
Solar + storage project IA-PNM-2021-21, Santa Fe County
Solar + storage
199 MWWithdrawn / abandoned Santa Fe, NMWest Oct 2021target 2024
Battery storage project C4-037, Salt Lake County
Battery storage
199 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Solar project C4-091, Bonneville County
Solar
199 MWWithdrawn / abandoned Bonneville, IDWest May 2024target 2028
Battery storage project C4-045, Walla Walla County
Battery storage
199 MWWithdrawn / abandoned Walla Walla, WAWest May 2024target 2028
Solar + storage project GI-2022-7, Arapahoe County
Solar + storage
199 MWWithdrawn / abandoned Arapahoe, COWest Mar 2022target 2025
Solar + storage project C2-61, Beaver County
Solar + storage
199 MWWithdrawn / abandoned Beaver, UTWest May 2022target 2025
Battery storage project GI-2022-3, Weld County
Battery storage
199 MWWithdrawn / abandoned Weld, COWest Mar 2022target 2025
Solar + storage project GI-2023-10, Arapahoe County
Solar + storage
199 MWWithdrawn / abandoned Arapahoe, COWest May 2023target 2026
Solar + storage project C3-121, Utah County
Solar + storage
199 MWWithdrawn / abandoned Utah, UTWest May 2023target 2027
Battery storage project C3-131, Salt Lake County
Battery storage
199 MWWithdrawn / abandoned Salt Lake, UTWest May 2023target 2027
Solar + storage project GI-TC-2024-24, Bent County
Solar + storage
199 MWWithdrawn / abandoned Bent, COWest May 2023target 2029
Battery storage project GI-2022-4, Weld County
Battery storage
199 MWWithdrawn / abandoned Weld, COWest Mar 2022target 2025
Battery storage project C3-100, Bannock County
Battery storage
199 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
Solar project C2-119, San Juan County
Solar
199 MWWithdrawn / abandoned San Juan, UTWest May 2022target 2025
Battery storage project C3-103, Klamath County
Battery storage
199 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2028
Solar + storage project IA-PNM-2019-20, San Juan County
Solar + storage
198 MWWithdrawn / abandoned San Juan, NMWest Apr 2019target 2022
Solar + storage project GI-2023-9, Pueblo County
Solar + storage
198 MWWithdrawn / abandoned Pueblo, COWest May 2023target 2027
Solar project 53, Thurston County
Solar
198 MWWithdrawn / abandoned Thurston, WAWest Oct 2017target 2019
Onshore wind project GI-2008-6, Huerfano County
Onshore wind
198 MWWithdrawn / abandoned Huerfano, COWest Jun 2008target 2009
Onshore wind project IA-PNM-2013-02, Roosevelt County
Onshore wind
198 MWWithdrawn / abandoned Roosevelt, NMWest May 2013target 2014
Solar + storage project C4-012, Iron County
Solar + storage
198 MWWithdrawn / abandoned Iron, UTWest Apr 2024target 2027
Onshore wind project 131, Garfield County
Onshore wind
198 MWWithdrawn / abandoned Garfield, WAWest Feb 2022target 2024
Solar + storage project IA-PNM-2019-16, Torrance County
Solar + storage
198 MWWithdrawn / abandoned Torrance, NMWest Apr 2019target 2024
Gas project Q42, Pinal County
Gas
197 MWWithdrawn / abandoned Pinal, AZWest Jul 2017target 2024
Page 38 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)