United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in California (2023 requests) β€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11856.5 GW
Active in queue56.5 GW118 requests
Agreement signed0.0 MW0 requests
Withdrawn481189.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

118 requests Β· page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Voyager Energy Storage
Battery storage
105 MWIn study Kern, CACAISO Apr 2023target 2027
Ulua
Battery storage
105 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Tioga Pass
Battery storage
103 MWIn study San Joaquin, CACAISO Apr 2023target 2028
Bonita Bateria
Battery storage
103 MWIn study Orange, CACAISO Apr 2023target 2029
Cassia
Battery storage
102 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Droga
Battery storage
102 MWIn study Merced, CACAISO Apr 2023target 2028
Solar + storage project 2023-G4, Butte County
Solar + storage
100 MWIn study Butte, CAWest Aug 2023target 2028
Solar + storage project GI-2023-171, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Apr 2023target 2026
Battery storage project GI-2023-166, Imperial County
Battery storage
100 MWIn study Imperial, CAWest Jan 2023target 2024
Battery storage project GI-2023-169, Imperial County
Battery storage
90.0 MWIn study Imperial, CAWest Apr 2023target 2025
Battery storage project GI-2023-178, Imperial County
Battery storage
75.0 MWIn study Imperial, CAWest Jun 2023target 2025
Off Stream Water Storage
Battery storage
68.9 MWIn study Colusa, CACAISO Apr 2023target 2030
Box
Solar
63.4 MWIn study Riverside, CACAISO Apr 2023target 2029
Little Hill
Battery storage
63.1 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Solar + storage project GI-2023-165, Imperial County
Solar + storage
50.0 MWIn study Imperial, CAWest Jan 2023target 2025
Solar + storage project GI-2023-172, Imperial County
Solar + storage
39.2 MWIn study Imperial, CAWest Apr 2023target 2025
Geothermal project GI-2023-177, Imperial County
Geothermal
33.0 MWIn study Imperial, CAWest Apr 2023target 2026
Separator Expansion
Battery storage
12.6 MWIn study San Bernardino, CACAISO Apr 2023target 2025
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)